OPR Report_031015 (2).pptx

OPR Briefing
Jerry Smith
OPS & Systems Engineering
harris.com
NON-Export Controlled Information
OPR Status Report 3/10/14
Harris Share Point
•
278 Total OPR’s To Date:
–
–
36 Added This Period
241 Closed To Date
•
55 Closed This Period
–
–
–
–
–
–
–
–
32 Issues Under Investigation
•
–
•
9 Timer Events
8 Log On Events
3 Recon Events
3 DM25 Events
3 A623 Events
2 Avionics Events
27 Other Events
10 Issues Being Investigated This Period
5 Open OPR Items To Be Distributed
7 Event Buckets
–
–
–
–
–
–
–
Timer Events
Log On Events
Recon Events
DM25 Events
A623 Events
Avionics Event
Other Events
CR1, SATCOM, Pilot Latency
No Correlation, No Log On
Channel Promotion
No DM25 ever sent from Flight Deck
Pilot requested A623 vs. DCL FANS
Discarded uplink, VDR issue, CMU issue
AC Loses Power, TMU 6-10, False Dep. Data Base
NON-Export Controlled Information
OPR Status Report 3/10/14
Event Totals
KEWR
KMEM
TOTALS
Timer
15
12
27
Logon
17
20
37
Recon
6
8
14
DM25
12
8
20
A623
5
20
25
Avionics
10
8
18
Other
58
42
100
Total = 241