TDLS Post IOC Build Release Plan revA.pptx

TDLS Post IOC Build Release Plan (S1P1)
Build Release
•
•
Ship Date
System Size
(PTRs / ERs)
Major Content & Build Criteria
Full Screen Implemented
Split PDC/CPDLC Screens w/Gates in Processed Tab
2 PDC & 3 CPDLC columns
TDLS v12.0
04/17/15
30 PTRs
3 ERs
TDLS/TIMS v12.0.1
05/21/15
Original - 15 PTRs
TEDC fixes needed for Phase 1 (TEDC Turnup)
Final - 41 PTRs
TDLS/TIMS v12.0.2
07/08/15
30 PTRs
CPDLC IOC Criteria - Safety, Stability, SLC fixes, useability/user
acceptance, \
TDLS/TIMS v12.0.3
CPDLC Non-National
08/07/15
IOC+30
20 PTRs
CPDLC IOC Criteria - Safety, Stability, IAH/HOU fixes,
useability/user acceptance,
TDLS/TIMS v12.0.4
UBER CHI Build and PTR fixes
11/6/2015
IOC+90
50 PTRs
Chi ERs
“New” CHI (Based on Thin Spec finalized by 4/3/15)
Training updates - Individual Lessons Delivered as completed in
rolling fashion up to it.
TDLS v12.0.4
CPDLC Rollout
PTR / Post IOC fixes
12/18/15
10 PTRs
PTR Resolution
Expect monthly updates through deployment waterfall to address emerging requirements and bug fixes.
Current planned PTR fixes are to address bugs found in testing – no current flight deck impacts.
Data Comm Program
June 2015
Federal Aviation
Administration
1
Consolidated Timeline
5/21/2015
TDLS/TIMS v12.0.1
5/15/2015
6/1/2015
7/8/2015
8/7/2015
TDLS/TIMS v12.0.2 TDLS/TIMS v12.0.3
7/1/2015
6/15/2015
MD-11 Pegasus-622 Release
3/15/2015
B737 U11 Release
Data Comm Program
June 2015
8/1/2015
11/6/2015
TDLS/TIMS v12.0.4 (KS)
9/1/2015
10/1/2015
11/1/2015
12/18/2015
TDLS v12.0.4 (Rollout)
12/1/2015
1/1/2016
2/1/2016
3/1/2016
3/15/2016
1/15/2016
B737 U12 Release
Federal Aviation
Administration
2