En Route Trials Status DCIT 41_Inwork.pptx

En Route Trials / Risk Mitigation
DCIT 40
John Glassley
Andria Roney
Jerry Smith
harris.com
NON-Export Controlled Information
Objective
• The purpose of the En Route Trials is to assess the requirements, architecture,
interfaces, and message loadability with in-flight aircraft using the “as-built” Lockheed
Martin prototype in the conduct.
• This effort will enable route loadability testing with DCIT partners in operational En Route
airspace with minimal impact to controller and flight deck operations.
• Route Messaging available in prototype for testing
–
–
–
–
–
–
–
–
–
–
UM74 (PROCEED DIRECT TO [position])
UM79 (CLEARED TO [position] VIA [routeclearance])
UM80 (CLEARED [routeclearance])
UM83(AT [position] CLEARED [routeclearance])
UM137 (Confirmed Assigned Route)
DM40 (Assigned Route)
DM0 (WILCO)
DM3 (Roger )
UM169 (Free Text)
UM117 – CONTACT [unit name] [frequency]
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 2
Concept of Operations
• En Route Trials Test Increments
Preparation and Coordination
1. Ground conduct with FAA Global 5000 in FAA hanger
2. Airborne conduct with an existing FAA Global-5000 in a dedicated holding
pattern in DCNS ACY volume of airspace near Atlantic City airport
3. Airborne conduct using the existing FAA Global-5000 aircraft in Kansas
City airspace
4. Airborne conduct using DCIT operational aircraft in Kansas City airspace
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 3
Schedule
Page 1
9/17/13
2015
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
'15
Implementation and
Operations Plan
4/1
Coordination Activities
4/1
Plan
Development
Adaptation
Update
8/20
Adaptation
Update
6/25
Operational Safety
Review with NATCA
Adaptation
Update
10/15
O&IP
5/1
Review CDRL
with FAA
10/16
Coord with airlines including
Global 5000, UPS, FedEx, United
and facilities: ZKC, WJHTC, ZDC, ZID
Incrememt 1 - FAA Global
5000 on the Ground
Briefings to DCIT,
facilities, and
stakeholders
Coord/Set up
at WJHTC
ZDC Adapt and
Inc 1 and 2 Scenario/VTL
4/20
Coord with Global
5000 Test Flight
Coord begins for
Operational Test Flight
Final Coord for Operational Test Flight
7/24
Debrief
6/11
Voice Comm Coord and Checkout
Hanger Coord and Checkout
Data Comm Lab Sched Coord
Incrememt 2 - FAA Global
5000 in a Holding Pattern in
ACY Airspace
7/20 7/24
Dry Run / Test
Global 5000 in hanger
7/31
Debrief
7/27
Dry Run / Test
Global 5000 in holding pattern
Incrememt 3 - FAA Global
5000 in non-ACY Airspace ZKC
8/14
7/6
Debrief
8/11
ZID/AKC Adapt and
Inc 3 and 4 Scenario/VTL
Global 5000 flights to
non-ACY loc
Early Operational AC
testing (on the ground)
10/30
Incrememt 4 - Operational
Aircraft in KSC
10/16
8/20
8/26 8/31
Confirm
FP/Adapt
Operational AC
Test in ZKC
Final
Debrief
Prep/Mtg
Updates to
Adaption if
needed
6/17/15
NON-Export Controlled Information
|
Presentation Name
|4
ZKC Meeting
• Met with ZKC
• Briefed ZKC Mgmt Team on En Route Trials Plan
• Collected PDARs and Sector Maps
• Observed live operations on midnight shift (2 pushes 10:30pm and 3am) and collected
times in sector, city pairs, and targets of opportunity data
• Significant flights west to east as well as east to west
• Collected strips for large number of flights
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 5
ZKC Ozark – Sectors 28-31, 33
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 6
WJHTC Meeting
• Teams identified
– Three NATCA representatives identified by Chad Geyer
– Additional support from Matt Maki and Steve Ferra (connection to Use Cases)
• Meeting with FAA and LM
• Determined that we can use the Lockheed “VTL Display lab” for the “home base”
• Provides optimal connection for the prototype with communication needed to the FAA
Global 5000 and telecom phone
• FAA Global 5000 pilots very engaged – will provide the coordination with the ZDC and
will file the flight plans that we work out for Increment 2 and 3
• Met with WJHTC and FAA Global 5000 pilots Jun 2
– Briefed En Route Trials Plan
– Discussed schedules and more details plans for performing tests
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 7
UPS Meeting
• Met with UPS June 3
– Briefed En Route Trials Plan
– Discussed potential flights that could be used for Trials for testing
– Looked at flight plans and discussed approaches
– Discussed potential flights that could be used for Trials. It appears that UPS can
potentially support 4 flights a week with one of their routes (west to east then west to
east pushes)
– Also looking at other flights as well
NON-Export Controlled Information
|
Presentation Name
6/28/2016 | 8
Schedule / Going Forward
• Implementation and Operations Plan – Final and accepted by FAA
– Briefed the plan with Chad Geyer/NATCA
• Coordination:
– FAA – during weekly tag up reviewed schedule and plan
– NATCA – Finalize training schedule
– En Route Trials Team – FAA, WJHTC, ZKC, FAA Global 5000, Carriers,
• Tag up meeting
– Carriers
• Meeting with FedEx and United
• Work with additional carriers – Delta, Southwest, American
– Detailed meeting with ZKC on July 16
• Flight plans, test scripts, etc.
• Training during Inc 2 Testing
• Increment Testing
– Inc 1 - July 2015 – FAA Global 5000 testing on the ground
– Inc 2 - July 2015 – FAA Global 5000 testing in a holding pattern in ACY airspace
– Inc 3 - August 2015 –
• FAA Global 5000 testing on a flight mission traversing multiple ARTCC boundaries (ZDC to ZID
to ZKC)
• Participating aircraft initial testing on the ground
– Inc 4 - Sept-Oct 2015 – Operational aircraft testing in Kansas City airspace