Data Communications Integration Team (DCIT) DCL Trials test activities Presented to: DCIT # 15 By: Peter Muraca FAA Date: May 30 – 31, 2012 Federal Aviation Administration Status • • Documents – Test Plan complete – E-E System Test Cases Document 85% complete – VRTM 90% complete – Working on SAT plan/procedures Coordination – ARINC and SITA service / connections – FAA FNTB – nesg gateway – T.C Project Aircraft – HADDS Lab for failover and revision change testing – Boeing Air Lab – DCIT Aircraft (FedEx, United, Delta) – A. Fry AIR LAB DCIT # 15 May 30 – 31, 2012 Federal Aviation Administration 2 Status - Test Activities start stop pDTAP delivery to Tech Center 5/10/2012 8/15/2012 pDTAP / HADDS in-box Interface Testing 5/14/2012 5/28/2012 pDTAP / HADDS via FNTB Interface Testing 5/28/2012 6/4/2012 pDTAP / HADDS / CSP Interface Testing via FNTB 6/4/2012 6/13/2012 pDTAP / HADDS / CSP / LAB Avionics Connectivity Testing via FNTB 6/13/2012 6/20/2012 pDTAP (applicable) Requirements Testing via Lab infrastructure 6/20/2012 7/18/2012 pDTAP (applicable) Requirements Testing via Lab infrastructure to Boeing Air Lab 7/18/2012 8/1/2012 pDTAP PTR fixes / Regression Testing in LAB env. 8/6/2012 8/15/2012 Test Plan Update 5/10/2012 7/20/2012 Test Cases Final 5/10/2012 7/20/2012 pDTAP Quick Look Report 7/11/2012 8/15/2012 DCIT # 15 May 30 – 31, 2012 Federal Aviation Administration 3 Status - Test Activities (cont.) DTAP End to End System Test 8/15/2012 10/12/2012 DTAP Requirements Testing using Lab Infrastructure (follow VRTM & Test Cases) 8/15/2012 9/14/2012 DTAP Requirements Testing using Lab Infrastructure with Test Aircraft (follow VRTM & Test Cases) 9/14/2012 9/21/2012 DTAP Requirements Testing using Lab Infrastructure with Boeing Air Lab (follow VRTM & Test Cases) 9/21/2012 9/28/2012 DTAP Requirements Testing using Lab Infrastructure with FedEx / Delta / United aircraft (follow VRTM & Test Cases) 9/28/2012 10/5/2012 DTAP Error Conditions / Abnormal Cases 8/5/2012 10/12/2012 DTAP PTR Fixes / Regression Testing 8/5/2012 10/12/2012 End to End Test Report 9/14/2012 10/12/2012 DCIT # 15 May 30 – 31, 2012 Federal Aviation Administration 4 Status - Test Activities (cont.) DTAP Site Acceptance Testing 10/15/2012 10/26/2012 Final SAT Sub_set Test Cases document 9/14/2012 10/12/2012 End to End Connectivity & Functional testing in field 10/15/2012 10/18/2012 Failover Conditions Testing 10/18/2012 10/20/2012 End to End Operational testing based on Sub_set Test Cases 10/15/2012 10/26/2012 SAT Final Test Report 10/15/2012 10/29/2012 DCIT # 15 May 30 – 31, 2012 Federal Aviation Administration 5 DCL Trials Architecture TOWER ARTCC FAA Technical Center FNTB DEMARC DATA RECORD FTI OS NESG ED-8 TEST ACY ED-8 ACY DTAP2 TDLS Strip Printer HADDS2,3 DTAP3 ERAM2,3 HID2,3 DTAP SITA HOST2,3 PC-RCU HID HOST DEMARC TOWER 3 HADDS ERAM OPS IP TOWER 2 TDLS ERAM FANS 1/A+ STACK MOUSE AFN HADDS ARINC DEMARC HMI KYBRD DCL HID DEMARC FDP HOST HADDS CSP & API MONITOR DTAP1 Airline HOST ARTCC2,3 Airline HOST