031413_DCIT.v1.mm_.ppt

Data Communications
Program
MEM/EWR ATCT DCL Trials
DCIT Update
To:
DCIT Plenary
From:
Matt Maki
Date:
03.14.2013
Federal Aviation
Administration
Agenda
•
MEM Trials Build 4.5 Limited Ops Summary
•
MEM Schedule Update
•
Build 6 Functional Testing Status
•
EWR Trials Schedule/Activities
•
EWR Participation
Federal Aviation
Administration
2
Build 4.5 Limited Ops Trials Complete
Date
Call Sign
FANS CPDLC DCL
DCL Result
Jan 17
FDX303 KMEM-KMIA
Cleared As Filed (CAF) Sent
FD - WILCO
Jan 18
FDX303 KMEM-KMIA
CAF Planned - Cancelled
AC Mechanical
Jan 22
FDX9056 KMEM-KMEM
CAF Planned
SW Failure – PTR
Jan 29
FDX303 KMEM-KMIA
CAF, UM79 Sent
FD – WILCO (2)
Feb 8
FDX993 KMEM-KOAK
Cleared As Filed (CAF) Sent
FD - WILCO
Feb 14
FDX303 KMEM-KMIA
CAF, UM79, UM79 Sent
FD – WILCO (3)
Feb 21
FDX303 KMEM-KMIA
CAF, UM79, UM79 Sent
FD – WILCO (3)
Feb 26
FDX303 KMEM-KMIA
CAF, UM79, UM79 Sent
FD – WILCO (3)
March 5
FDX303 KMEM-KMIA
CAF, UM79, UM79 Planned
HADDS Outage
March 6
FDX303 KMEM-KMIA
CAF, UM79, UM79 Planned
AFN, SW Failure
Federal Aviation
Administration
3
MEM Schedule Update – March 14
•
Planned MEM Schedule:
-
•
March 26: Start of 3 ops/day at MEM
April 30: Start of Full Ops 24x7 Trials at MEM
Adjusted MEM Schedule Outlook:
-
Updated to reflect Patch 3 required PTR fixes
Mid April: Start of 3 ops/day at MEM
Now TBD: Start of Full Ops 24x7 Trials at MEM
•
Firm Ops Schedule pending Critical PTR Patch 3
delivery/testing schedule from Thales
•
Additional Build 7 New Requirement Development OnGoing
Federal Aviation
Administration
4
Build 6 Functional Testing Update
•
Functional Testing On-going at WJHTC and MEM:
Testing approx. 85%+ complete at WJHTC
Daily 4pm Telcon to review daily testing/PTR creation
•
Build 6 Patch 3 planned to correct required functionality to
begin 3 ops/day Trials at MEM:
- Required PTR corrections identified by DCIT Ops
Management Group
•
Testing includes utilization of WJHTC, Boeing and Airbus
bench avionics
Federal Aviation
Administration
5
MEM, EWR ATC Training
•
ATC training underway at MEM:
-
•
Start 3/11, Finish 3/20
DTAP3 moved to EWR for first week in April:
-
EWR ATC Training under Harris DCIS tasking
Federal Aviation
Administration
6
EWR Trials Schedule/Activities
•
EWR DTAP4 Hardware scheduled for pickup at Thales on
March 15:
Will be driven to EWR ATCT
Build 6, EWR Adaptation installed
Space NCP approved
•
EWR DTAP4 equipment, cables and display installation at
EWR ATCT confirmed for the week of March 18
•
Team met with UPS on March 6 in Louisville:
UPS confirmed EWR Trials participation
UPS to provide live aircraft for ramp FANS/DCL testing
during Pre-SAT and SAT testing at both MEM and EWR
Initial MOU comments back from UPS
Federal Aviation
Administration
7
Additional EWR Participation
•
Initial planning telcon meeting scheduled
with British Airways on March 18:
-
2 B777 daily FANS EWR ops
BAW currently utilizes 623 DCL service at LHR
and Gatwick
BAW to assigned grounded pilots to effort
Federal Aviation
Administration
8