Agenda
•
Patch 4 Testing Status / MEM-EWR Installs
•
MEM / EWR Operational Trials Status/Results
•
Patch 5 / Build 7 Status
•
MEM Test NCP Extension: JW925-FDIO-1001 / T34501
Federal Aviation
Administration
2
Current DTAP Patch 4 Outlook

6/4:
Factory Acceptance Testing Completed @ Thales

6/5:
Patch 4 Installed at the WJHTC

6/6-14:
Patch 4 Testing at the WJHTC
•
6/17:
EWR Install
•
6/18-20:
EWR Pre-SAT Testing
•
6/24:
MEM Install (Includes UPS upgrade)
•
6/25-27:
MEM Pre-SAT Testing along with proposed 6/27
MGT demo - 24x7 Checkpoint
Federal Aviation
Administration
3
MEM Trials Current Status
•
Continued FDX Limited Ops (As of 6/13):
-
•
35 to 50 DCL ops ‘shakeout’ period (20 MD-11, 15 B777 ops minimums)
36 successful CAF DCL issued since April 17 start (28 MD-11, 8 B777)
34 CAF, 2 UM80 Initial DCLs Issued
5 UM79 , 3 UM80 Revisions issued
Additional ops up to 6/23 planned
MD-11 UM79 Revisions stopped after May 3 Op due to FDX FD
observed en-route FMS Map ‘To Point’ Magenta Line re-draw
(back to original route):
-
Boeing/Honeywell identified and can reproduce issue
Procedural Work around being presented to Flight Deck Working Group
at Boeing/Long Beach
EWR/UPS MD-11 to try to duplicate issue
MEM 24x7 Trials Ops ‘Go’ Date pending FDX work around acceptance
Federal Aviation
Administration
4
EWR Trials Current Status
•
Continued Limited Ops (As of 6/13):
-
6 successful CAF DCL issued since May 16 start (3 MD-11, 2 B777, 1
A340)
6 CAF DCLs Issued
2 UM79 , 1 UM80 Revisions issued
Additional ops up to 6/14 planned
Limited Trials Ops can resume 6/21
Additional ATC DTAP support expected after 6/21 or Refresher Training
-
•
Domestic and International Participation:



-
UPS
BAW
SAS
FDX (pending first Revenue operation)
DLH, DLH Cargo, Swiss Air (pending initial testing)
Federal Aviation
Administration
5
DTAP Patch 5 and Build 7 Status
•
DTAP Patch 5 Requirements / Delivery Status:
-
•
EWR ATC Requirements (4 Total)
Thales cost/schedule proposal currently undergoing Gov evaluation
Dual Contact / Drop Down Remarks proposal for a summer delivery
Remaining Requirements delivery proposal moved to late Fall
Combine remaining reqs with pending Build 7 proposal/estimate
Thales to Scope Build 7 Requirements for Scope, Schedule
Cost:
-
FAA options to select specific functionality based on schedule/cost
consideration
Build Contract Acceptance and Delivery to FAA currently TBD
Federal Aviation
Administration
6
MEM/EWR Test NCP Status
EWR Test NCPs:
MEM Test NCPs:
JW925-HNL-1004 / T34840
ZME HADDS Connection
(EXTENSION)
NAS CCB Approved – 5/2/2013
JW925-FDIO-1001 / T34501
MEM DTAP FDIO/PCRCU Echo
Port Connection
NCP Issuance Date - 8/25/2012
JW925-HNL-1003 / T34752
ZNY HADDS Connection
NAS CCB Approved – 5/2/2013
JW925-FDIO-1002 / T34753
EWR DTAP FDIO/PCRCU Echo
Port Connection
NAS CCB Approved – 5/2/2013
JW925-ATCT-1002 / T34759
EWR DTAP Equipment Space
ESA Approved – 3/4/2013
Federal Aviation
Administration
7
Questions ?