Test Procedure for the LV8772GEVB Evaluation Board
Function generator1
Hz
CHANNEL
Power supply 3
1
2
A
V
Multimeter
VOUT
-
+
-
+
Power supply 1
A
V
Power supply 2
A
-
V
+
-
+
Stepping Motor
CURRENT PROBE
AMPLIFIER 1
CURRENT PROBE
AMPLIFIER 2
PROBE
INPUT
PROBE
INPUT
OUTPUT
OUTPUT
Osclloscope
CHANNEL
1
2
3
4
Table1: Required Equipment
Equipment
Efficiency
35V-5A
5V-0.5A
10V-1A
200kHz
Power supply1
Power supply2
Power supply3
Function generator
Multimeter
Oscilloscope
Current probe1
Current probe2
LV8772 Evaluation Board
Stepper Motor
1/8/2014
4 channel
35V-3A
1
www.onsemi.com
Testing Procedure:
1. Connect the test setup as shown above.
2. Set it according to the following guide.
[Supply Voltage]
VM (9 to 32V): Power Supply for LSI
VREF (0 to 3V): Const. Current Control for Reference Voltage
VDD (2 to 5V): Logic “High” voltage for toggle switch
[Toggle Switch State] Upper Side: High (VDD)
Middle: Open, enable to external logic input
Lower Side: Low (GND)
[Operation Guide]
1. Initial Condition Setting: Set “Open” the toggle switch STEP, and “Open or Low” the
other switches.
2. Power Supply: Supply DC voltage to VM, VREF and VDD.
3. Ready for Operation from Standby State: Turn “High” the ST terminal toggle switch.
Channel 1 and 2 are into 2-phase excitement initial position (100%, -100%).
4. Motor Operation: Input the clock signal into the terminal STEP.
5. Other Setting
i. ATT1, ATT2: Motor current attenuation.
ii. RST: Initial Mode.
iii. FR: Motor rotation direction (CW / CCW) setting.
iv. MD1, MD2: Excitation mode.
3. Check VREG5 and VG terminal voltage at multimeter.
4. Check the STEP and MONI terminal voltage at scope CH1 and CH2, and the output current
waveform at scope CH3 and CH4.
Table2: Desired Results
INPUT
OUTPUT
VM=24V
VREG5=4.5V to 5.5V
VREF=1.5V
VG=28V to 29.8V
VDD=5V
ST=High
RST =Low
ATT1=ATT2=Low
FR =Low
MD1 =MD2 =High
STEP =500Hz (Duty50%)
1/8/2014