NCP1380DGEVB_TEST_PROCEDURE.PDF - 1913.0 KB

 Test Procedure for the NCP1380DGEVB Evaluation Board I ‐ Test Setup Figure 1: Test Setup 11/23/2011
1
www.onsemi.com
Required equipment: • Ac power supply: 85 – 265 Vrms, 2 A • Yokogawa power meter WT210 • Voltmeter • Electronic load: 19 V, up to 4 A II – Test Procedure 1. Make sure the S11 point is shorted as shown in Figure 2. Figure 2: aux. winding connection 2. Connect the equipments to the board as shown in Figure 1. 11/23/2011
2
www.onsemi.com
3. Apply an input voltage from 85 Vrms to 265 Vrms, 50 Hz or 60 Hz. 4. Do the measurements listed in the below table. Measurements
1
Output voltage
Conditions
Vin = 115 Vrms
No output load
Results
2
Input power consumption at
high line and no load
Vin = 230 Vrms
No output load
Pin ≤ 0.110 W
Vout = 19 V +/- 5%
3
Input power consumption at
high line and low output load
Vin = 230 Vrms
Pout = 0.5 W
4
Efficiency at low line and full
load
Vin = 115 Vrms
Pout = 60 W
5
Efficiency at high line and full Vin = 230 Vrms
load
Pout = 60 W
Pin < 0.75 W
Vout = 19 V
Pin < 67.42 W or
efficiency > 89%
Vout = 19 V +/- 5%
Pin < 67 W or efficiency
> 89.5%
Vout = 19 V +/- 5%
6
Maximum output power at
high line
Vin = 230 Vrms
Increase Iout
7
Brown-Out
Decrease Vin until Vout = 0 V
Pout = 3 W
Comments
Vout = 19 V +/- 5%
Pout(MAX) = 82 W +/- 5%
Vin = 45 Vrms +/- 10%
No load measurement
can fluctuate, run
WT210 in average mode.
NCP1380B shuts down
and tries to restart.
NCP1380A is latched.
Output voltage must
collapse below 50 Vrms
11/23/2011
3
www.onsemi.com