Key Site Timelines Federal Aviation Administration Hal Ludwig & Pete Muraca Data Comm Federal Aviation Administration 1 Accomplishments Since Last DCIT • • • • SLC IOC Declared 8/7/2015 IAH and HOU upgraded to TDLS V.12 SW HOU TDLS-ERAM Direct Connect Interface is operational International Flights – Hyphen issue for non-US Flag carriers will be fixed in release on 9/10 – International flights for all carriers only CAF initially (revision by voice only) – Resolved prior to waterfall. • Coordinated with first set of waterfall sites – – ZHU ZID ZNY – held first two coord mtgs – • On track for IOC at MSY, SDF, and EWR. • Aug. 25 kickoff with second set of waterfall sites (ZLA, ZME, ZBW, ZDV) Data Comm Federal Aviation Administration 2 SLC Test Status-IOC Declared • Operators Supported Testing leading up to IOC at Salt Lake City ̶ FedEx Express (MD11) ̶ UPS (B767 & MD11) ̶ United Airlines (B737-900) ̶ Southwest Airlines (B737-800) ̶ Harris Corporation (Falcon 9) ̶ US Air Force (KC-135) Data Comm Federal Aviation Administration 3 2015 Path to ISD You are here JUL AUG SEPT EAD30 OCT V12.0.2 7/15 CPDLC - SLC V12.0.3 7/22 V12.0.3.xxx Int’l Flights 9/10 IAH/HOU 8/14 V12.0.2 V12.0.4 V12.0.5 Enhanced CHI 11/6 9/18 V12.0.2 DEC 10/22 TDLS V12.0.2 NOV EAD40 Test only 7/1 Draft v5.1 12/18 Thanksgiving 11/21 TIMS Field Activities ZTL 8/17 SLC 7/23-25 Network IAH HOU 8/5 7/16-18 IAH 7/30 - 8/1 ZLC/SLC TO & FM Testing P3 ZLC P1 IAH TEDC TEDC 8/6-8/12 Phase 3 ZLC/SLC DFV Dry run & Conduct 7/21 = ERAM V12.XX SLC = TDLS V12.XX ZTL = TIMS Data Comm Milestones 7/9-11 P1 HOU 8/3-4 8/31 9/4 SLC BOI HOU 7/6 - 7/9 Testing & SSM-220 8/15-17 7/29 – 8/5 8/7 Phase 4 ZHU/IAH/HOU DFV Dry Run & Conduct 8/19 8/13-17 1/4 SLC BOI IAH HOU Phase 5 ZLC/ZTL Nat’l Site Failover 8/18-20 P4 12/19 SLC BOI IAH HOU Connectivity BOI 11/30 ARTCC EAD40 Install SLC BOI IAH HOU 8/27 TIMS 8/5 uplevel to DC EADXX 8/13 ZTL EAD30 Install SLC BOI ZLC EAD30 Install ZLC/ZHU Parent/Nat’l Integration P0 ZHU ERAM ZHU EAD30 Install Christmas 9/10 9/30 9/10 ZLC/SLC IOC ZHU IAH IOC ZHU HOU IOC ZLC ZTL IOA Complete Complete ISD 8/7 9/3 9/10 9/30 11/30 12/09 Federal Aviation Administration 4 KIAH – Carrier DFV Participation Lead-Up Timeline 5/18 IAH Coordination Meeting Coordinate Detailed KIAH DFV Schedule with Participants 8 /11 Final Test Scripts Provided to Participants 8/28 - 9/3 8/19 - 8/27 Jun -15 Jul -15 Aug-15 9/3 KIAH IOC Sep -15 May-15 Sep -15 9/3 KIAH IOC 8/19 - 8/21 Testing w / WJHTC 8/19 - 8/27 8/19 - 8/27 Dry Run w / Tech Center Avionics and Carrier KIAH DFV Dry Run Aug -15 Data Comm 8/28 8/28 - 9/3 - 9/3 DFV - File and Fly Flights KIAH DFV Conduct Sep -15 8/22 - 8/27 Testing w / Carrier Federal Aviation Administration 5 Testing Window Tentative ERAM Mid-Shift Active and Back-Up mode KIAH Date Testing w/ WJHTC 08/19 – 08/21 W, Th, F Testing w/ Carrier 08/22 – 08/23 Sa, Su Mid-Shift Active and Back-Up mode Testing w/ Carrier 08/24 – 08/27 M, Tu, W, Th Mid-Shift or Day & Swing Shift (as Aircraft avail.) Active and Back-Up mode Carrier File and Fly 08/28 – 09/03 F, Sa, Su, M, Tu, W, Th Normal Ops Active and Back-up mode IOC 9/3 Dispatch (FPL Filing) Local Flight Deck Remote Flight Deck AOC System Note: Mid-Shift is 2200-0300 or 0500 (Local) Data Comm Federal Aviation Administration 6 IAH Test Status • Conduct DFV field testing @ IAH with the following major carriers and test facilities: – – – – UPS UAL FDX FAA Technical Center Bench Avionics (B757 / 767, B737) Data Comm Federal Aviation Administration 7 KHOU – Carrier DFV Participation Lead-Up Timeline 5/12 KHOU Coordination Meeting Coordinate Detailed KHOU DFV Schedule with Participants 7/9 Final Test Scripts Provided to Participants 9/10 KHOU IOC 9/3 - 9/10 8/24 - 9/2 Jun-15 Jul-15 Aug -15 Sep -15 May-15 Oct -15 Oct -15 9/10 KHOU IOC 8/24 - 8/26 Testing w / WJHTC 8/24 - 9/2 8/24 - 9/2 Dry Run w / Tech Center Avionics and Carrier KHOU DFV Dry -Run Aug-15 9/3 9/3- 9/10 - 9/10 DFVKHOU - File DFV and Fly Conduct Flights KHOU DFV Conduct Sep-15 8/27 - 9/2 Testing w / Carrier Data Comm Federal Aviation Administration 8 KHOU Date Testing w/ WJHTC 08/24 – 08/26 M, Tu, W Testing w/ Carrier 08/27 – 08/28 Th, F Testing w/ Carrier 08/29 – 09/02 Sa, Su, M, Tu, W Carrier File and Fly 009/03 – 09/10 Th, F, Sa, Su, M, Tu, W, Th IOC 9/10 Testing Window Tentative ERAM Mid-Shift Active and Back-Up mode Mid-Shift Active and Back-Up mode Mid-Shift or Day & Swing Shift (as Aircraft avail.) Active and Back-Up mode Normal Ops Active and Back-up mode Dispatch (FPL Filing) Local Flight Deck Remote Flight Deck AOC System Note: Mid-Shift is 2200-0300 or 0500 (Local) Data Comm Federal Aviation Administration 9 HOU Test Status • Conduct DFV field testing @ HOU with the following major carriers: – – – – – UPS SWA UAL FDX FAA Technical Center Bench Avionics (B757 / 767, B737) Data Comm Federal Aviation Administration 10 AOC Interface Scorecard • Completed testing with UPS, FDX, and UAL • Working with USAF TACC to test Interface • SWA working based on SLC testing. Data Comm Federal Aviation Administration 11 Discussion Items • TDLS Updated IRD Review – IRD Rev A has NAS CCB approval • Interface is available for test (WJHTC and IFCET) – IRD Rev B NAS CCB approval • SDB Inputs – Web interface activation delayed for additional testing. • SLC Daily Test Coordination Meeting Feedback Data Comm Federal Aviation Administration 12