Presentation1

NEC’s Submarine Cable System
December 5, 2008
NEC Corporation
Broadband Network Operations Unit
Executive General Manager
Masamichi Imai
1. Outline of Submarine Cable Systems
2
© NEC Corporation 2008
1-1. The History of Submarine Cables
1850:First Telegraph cable at Dover Strait
1858:First Trans-Atlantic Telegraph Cable
(1876:Graham Bell invents the Telephone)
1906: Submarine Cable Tokyo-Guam
1956:First Trans-Atlantic Coaxial Cable
(1963: Satellite Communications between Japan and US begins)
1964:First Trans-Pacific Coaxial Cable
1988:First Trans-Oceanic Optical Cable(1 Gb/s)
1999:Trans-Oceanic Optical Cable (640 Gb/s)
2001:Trans-Oceanic Optical Cable (1.28~Tb/s)
3
1-2. Summary of Submarine Cable Systems
Station A
Station B
・Burial up to sea depth of
1500m
Max. Sea Depth 8,000m
・Avg 1m-3m burial (Max.15m)
(at 8000m below sea level, water
pressure is equivalent to holding a
car on one’s thumb.)
= Repeater
Placed at 40Km~100km intervals
←Cables are laid in deep trenches
Max. Transmission Distance 12,000~13,000km
Japan to US West Coast is approx. 8,000km
At least 80~100 repeaters are required.
4
1-3. Components of a Submarine Cable System
Wet Side
Dry Side
Submarine Repeater
Line Terminal Equipment
Submarine Cables (inc.. fiber.)
Power Feeding Equipment
Supervisory System
Overall System Monitoring
Repeater Performance Monitoring
5
Network Protection Equipment
(SDH system)
Installation Cableship
1-4. Technical Trends
Coaxial
Fiber Optics
40G DWDM
Optical
Amplifier
10G DWDM
System 2.5G DWDM
5G Single
Optical Regenerator
System 1.3 / 1.55 μm
Coaxial Repeater
System
1970
6
1980
1990
2000
Now
1-5. Transmission Capability
2.56T
Coaxial
Repeaters
Optical
Amplifier
Optical
Regenerator
40G x 96
5th Gen.
WDM
10G x 192
40Gb/s WDM
System Based
1.28T
960G
10G x 128
640G
Bit Rate (Bit/s) / Fiber Pair
320G
160G
20G
10G x 96
10Gb/s WDM
System Based
4th Generation
WDM
10G x 64
10G x 32
10G x 16
System
2.5Gb/s WDM
System Based
Planned
2.5G x 8
Ongoing
10G
5G
3rd Generation
Single
Wavelength
2.5G x 4
Installed
5G
1.44G
2.5G
2nd Generation
1.55μm
560M / 622M
1G
420M
500M
1st Generation
1.3μm
140M/280M(TPC3)
100M
7
'82
'84
'86
'88
'90
'92
Year
'94
'96
'98
‘00
‘02
‘04
‘06
‘08
‘10
1-6. Latest Transmission Capacity
The Maximum Transmission Capacity for the latest
Submarine Cable System, using the latest Optical
Transmission technologies, is 10.24 Terabits/sec.
◆So, how fast is 10.24Tbps ?
1Cable can carry
Approx. 160Mil. Telephone Circuits
simultaneously
or
1Cable can send
Approx. 272 DVD Disks
between continents within 1 second.
10.24 Tbps
10.24Tbps = 10Gbps x 128WDM x 8fiber pairs
a) 10Gbps:
b) 128WDM:
c) 8fiber pairs:
8
1 wavelength (color) can carry 10Gbps worth of data
1 fiber can carry wavelengths (colors) up to 128 colors
1 Submarine Cable can accommodate up to 8 fiber pairs.
1-7. Comparison between Submarine Cable and
Satellite Communications
1. Enables Highly Reliable and Affordable Broadband Communications
1) Suitable for Communications
2) Adaptable to various Applications
-HD Digital
-High Speed
-High Speed
-High Speed
Television
Internet Connection
Mobile Communications
Data Transmission, etc.
Satellite Communications
・Latency
:250ms
・Design Life:10~15years
・Capacity
:48,000ch
2. Easily Upgradable plus Long Lifespan
1) Upgrade only when necessary
-Upgradable with minimum investment
2) 25 year Design Life
Optical
Submarine
Cable
9
Optical Subsea Communication
・Latency
:50ms
8,500km
・Design Life :25years
・Capacity
:80,000,000ch
(10Gbits,128WDM,4fp)
2. Features of Submarine Cable Systems
10
© NEC Corporation 2008
2-1. Submarine Cable Projects
Features
¾ Infrastructure for Int’l Traffic
(Construction Period 10~18 Months)
¾ Large Capacity Transmission
¾ System Design Life 25 years
Project Formation
NEC
System Design
Subsea Repeaters
Line Terminals
Power Feed
Integration
Project Management
11
Cable
Marine
OCC
NTT・WEM
KCS
KTS
ACPL
others
2-2. Flow of a Typical Project
→
End of Warranty
Provisional
→
Acceptance
(Commercial)
Down Payment
→
PJ Commence
Contract Sign
Project Duration:6~8 years
(from RFP to System Completion: 1~3years
Warranty Period
Implementation
Of Project
Contract Negotiations
Clarification Meetings
( ~ times)
Create Proposal
3
→
Select Vendor
→
Submit Proposal
→
RFP Release
12
2
2yr~5yrs
1yr-2yr
2wks~ 1Mo~6Mo 2wks~
4wks
4wks
2-3. Construction of New Cable vs. Upgrade
Construction of a New Cable ≒ Like building a 10 lane expressway (but use only 1 lane)
Capacity Upgrade ≒ Like opening one lane at a time. No New Construction.
・ Constructing a New Cable is like constructing a 10 lane expressway but using only
1 lane at the beginning. If traffic increases, more lanes will be opened.
・ A 10 lane expressway costs more to build than a 1 lane expressway, but is less
than building ten 1 lane expressways. Initial investment works out to be high, but
are being build to cope with future demands.
13
© NEC Corporation 2008
3. Submarine Cable Systems Market
14
© NEC Corporation 2008
3-1. Global Trends
(US$ Million)
10,000
■Demands were high
during 1999-2001,
but a 20 year trend
seems stable at
US$2,100M~2,500M
9,800
Order Basis
Market Size
9,000
Upgrades
8,000
Average
7,000
Average
(Upgrades)
6,000
5,000
4,000
7,182
3,000
2,642
2,190
2,085
2,000
1,976 2,6362,570 2,871
3,032
2,952
2,500 2,500
■CAGR of Upgrades is
approx. 100.2%
2,578
2,170
1,477
1,000
612
854
1,161
1,921
1,225
107 257
508
711
420
0
(a/t NEC)
Optical 3R Optical Amplifier 2.5G
(5G)
WDM
15
10G WDM
■2007 saw demands
coming back to mid
90’s level. Expect
moderate growth for
coming years
■Expect high demands
in Asia-Pacific, Indian
Ocean, Middle East
and Africa
4. NEC’s Strategy towards Submarine Cable
Systems
16
© NEC Corporation 2008
4-1. NEC’s Strategy for Submarine Cable Systems
1. Focus on the Asia-Pacific region(Maintain regional strength)
•
Produce High Quality products from Ohtsuki plant(25 year warranty)
•
Focus marketing resources to Asia-Pacific
2. Maintain Stable Growth
•
Total Supply from Terminal Equipments to Repeaters & Cable
Stable Supply made possible with acquisition of OCC
•
Maintaining Profitability while Minimizing Risk
•
Avoid High-risk / High-return projects, and maintain stable growth
3. Spin-Off ~ Ocean Bottom Seismograph Systems
・Sole supplier of Ocean Bottom Seismograph Systems in Japan
・Detect “P-wave” from earthquakes for the Meteorological Agency’s
“Earthquake Early Warning System”
17
4-2. Status of the Submarine Industry(Top 3 suppliers)
Tyco
Alcatel
NEC
System Integration
Manufacture of
Submarine Line
Terminal Equipment
Manufacture of
Submarine
Repeaters
Manufacture of
Submarine Cables
Marine Work &
Maintenance
Cable Install
Company
Cable Install
Company
Cable Install
Company
・ Top 2 Suppliers can manufacture, integrate and implement, and
provide Maintenance Services with own resources within.
・ By acquiring OCC, NEC is now able to provide services nearly
equal to the top 2 suppliers.
18
4-3. Structure of OCC Aquisition
Acquired interest of OCC Holdings
(Before)
Longreach Group
(After July 15, 2008)
Sumitomo Electric
Industries
NEC
Approx.75%
(100%)
OCC Holdings
OCC Holdings
(100%)
(100%)
OCC
Approx.25%
OCC
NEC Corporation and Sumitomo Electric Industries acquired
OCC Holdings from the Longreach Group.
19
4-4. Company Overview for OCC
20
Operations
Subsea Cable:Design, Manufacture and Sales of
Communication purpose Submarine Cable and
Surveillance cables.
Terrestrial Cable:Manufacture and Sales of Communication
purpose Terrestrial Cables.
Offices
Head Office
:Yokohama, Japan
Plants:
Submarine Cable (City of Kita-Kyushu)
Terrestrial Cable (Kaminokawa Township)
Founded
June 1935
Capital
2.255 Billion Yen (as of March 2008)
Sales
17.46 Billion Yen (for year ending March 2008)
Director
Yoshihisa Okada, President and CEO
Employees
Approx. 221 pax. (not including directors and temp.staff)
Shareholders
OCC Holdings (100%)
4-5. Ocean Bottom Seismograph System
・Constantly transmits data gathered from the Seismograph through Optical
Fiber Cable to the Terrestrial Station.
・Technology base: NEC’s Submarine Cable System and Subsea Equipment
(Features)・Enables real-time monitoring of seismic activities 24/7
・Enables Tsunami readings off the coast before reaching the shores.
・Enables Reliable and Stable Monitoring
Line Terminal Equipment
Ocean Bottom
Seismograph
Optical Fiber Cable
Tsunami
21
Earthquake
4-6. Seismograph System of Omaezaki
Seismograph System around Japan
Features
JMA: Japan Meteorological Agency
-Installed as part of strengthening the
observation system of Tokai area
ERI: Earthquake Research Institute,
University of Tokyo
NIED: National Research Institute for Earth
science and Disaster Prevention
(JAMSTEC, 1999)
JAMSTEC: Japan Agency for Marine-Earth
Science and Technology
5 Sanriku
7 Kushiro
(ERI, 1996)
Note:
Optical Fiber
Coaxial
2 Katsuura (JMA,
1986)
4 Hiratsuka (NIED, 1996)
6 Muroto
(JAMSTEC, 1997)
1 Omaezaki
(JMA, 1979)
3 Itoh (ERI, 1993)
8 Omaezaki
-NEC was selected as supplier for this
project on the followed account;
1. In 1976, NEC supplied the first Ocean
Bottom Seismograph System to JMA
2. NEC is the only supplier of Ocean
Bottom Seismograph System and has
a supply record of 7 systems around
Japan
(JMA, 2008)
Installation Completed
Project Outline
z Customer: JMA
z Installation completed for the first 2 year
phase (Project Duration : total 4 years)
z Scope of work: Supplying Ocean Bottom
Seismograph/ Tsunami gauge
22
Future outlook
◆Upgrade project of Hiratsuka, and
New projects in Sanriku and Kii Peninsula
23