Download Presentation

API 541 5th Edition
Revisions, Updates & Improvements
Unrestricted © Siemens 2016
usa.siemens.com/oil-and-gas
Outline of Presentation
 Introduction
 What is API 541 & when do I use it?




Timing/process of revision
Notable changes
How to optimize the use of API 541
Conclusions
Unrestricted © Siemens 2016
Page 2
Confused by Standards?
500 kVA
≥500kVA
Synchronous machines
API 546 3rd
‘Custom’
API 541 5th
2 pole WPII
2 pole TEFC
‘Standard’
≥500HP
API 547 1st
Vertical
250 – 3000HP 4/6/8p
“Non-critical”
IEEE 841 2009
≤500HP, ≤4kV, TEFC
H & V, A/F brgs
HP 1
kW
Unrestricted © Siemens 2016
Page 3
250
185
500
375
800 1250
600 930
3000
2240
10000
Now metric
100000
Introduction
 API 541 5th Edition
 Form wound, cage induction motors
 Induction generators too
 375kW (500HP) and larger
 Horizontal or vertical
 ANSI/IEEE/NEMA or IEC/ISO
 Metric units (with US customary)
 General industry not just API
Unrestricted © Siemens 2016
Page 4
Timing/Process of Revision
 Working group assembled April 2008
 End users, Consultants . . . and motor OEMs
 Open discussions on suggested improvements
 Incorporate API 546 revisions as appropriate
 Sub-groups to discuss/recommend broader changes
 Ballot (second) approval May 2011
 Print proof reviewed in July 2012
 Published December 2014
Unrestricted © Siemens 2016
Page 5
Why Use API 541?
 Standard specification that provides customized product




Simplifies machine definition
Simplifies proposal preparation
Simplifies proposal evaluation
Provides for a reliable machine
 Utilizes comprehensive data sheets
 Important to everyone involved from manufacturer to user
Unrestricted © Siemens 2016
Page 6
Notable Changes








Service factor
Thermal capacity data
Insulation temperature limits
Magnetic stator slot wedges
Totally enclosed default (≥6kV)
Torsional stress evaluation
Surge capacitors
AC hi-pot testing
Unrestricted © Siemens 2016
Page 7







Frame vibrations
Unbalanced response test
Stator core test
Sample coil & pd testing
Heat exchanger testing
Coil data
Data sheet & guide
Revised
Service Factor
 Motors shall have a service factor of 1.0
 If overload capacity is required, a higher nominal motor rating shall be selected
 Avoids operating motors above rated power, which increases winding temperatures and
shortens motor life
Unrestricted © Siemens 2016
Page 8
Revised
Service Factor
 NEMA MG1
100
90
80
Percentage of life (%)
 Allows 10°C increase in temperature rise when
operating at 1.15SF
 Regardless of voltage, HP, insulation class or
measurement method
 Rule of thumb
 10°C increase ≈ ½ insulation life
70
60
50
40
30
20
10
0
0
10 20 30 40 50 60 70 80 90 100
Additional temperature (˚C)
Unrestricted © Siemens 2016
Page 9
Revised
Thermal Capacity Data
 Supplier now required to provide thermal capacity data, including:
 Thermal limit curves
 Acceleration curves
 Required stop/running cool times after max starts
 Useful for programming motor protection relays
Unrestricted © Siemens 2016
Page 10
Revised
Thermal Capacity Data
 Thermal limit curves
 Comply with IEEE Std 620-1996 (R2008)
 Ambient and rated running temperature
Running overload
Accelerating
Locked rotor
Time-current
Unrestricted © Siemens 2016
Page 11
Revised
Insulation Temperature Limits
 RTDs measure “hot spot” temperature
 RTDs inserted between coils in the slots
 Average temperature determined by change
of winding resistance
 Permitted hot spot rises are 0 to 10°C above
average rises
Unrestricted © Siemens 2016
Page 12
 Occasionally average exceeds hot spot
meaning hot spot is not the worst case
 Now required to meet the limits by both
methods
 Ensures temperature limits are met
throughout windings
New
Magnetic Stator Slot Wedges
 Not previously been addressed
 Used by many vendors and can improve
performance but some have durability issues
 Requirements –
 Rigid and VPI’d in place, amorphous or
composite construction, 10 year track record,
630 mm shaft height limitation
Unrestricted © Siemens 2016
Page 13
New
Totally Enclosed ≥ 6kV
 For example TEAAC or TEWAC
 Default requirement
TEAAC/CACA
 Free to specify open enclosure if good
experience at site
 Minimizes airborne contaminants
 Reduced risk of electrical tracking
 Reduced risk of early winding failure
TEWAC/CACW
Unrestricted © Siemens 2016
Page 14
Revised
Torsional Stress Evaluation
 Torsional oscillations don’t just break shafts
and couplings!
 Now specify fatigue analysis of fans and rotor
bar overhangs for applications involving
torsional oscillations
 Require infinite fatigue life
 Analyze applied stresses, resonances,
metallurgy and stress concentration
Unrestricted © Siemens 2016
Page 15
Revised
Surge Capacitors
 Surge capacitors reduce the steepness of
surges at the terminals
 Reduce stresses between turns of coils
 Now call for three single phase capacitors
instead of a single three phase unit
 Reduce consequent damage from a capacitor
failure
CTs
Surge
capacitors
Unrestricted © Siemens 2016
Page 16
Surge
arresters
Revised
AC Hi-Potential Testing






AC ‘hipot’ is a standard test before shipping
Voltage = (2 x rated voltage) + 1kV AC
There is no pass/fail criterion defined in other standards
Now require document leakage current, temperature and humidity
Observe end windings for arcing
No rapid voltage/current fluctuations
Unrestricted © Siemens 2016
Page 17
New
Frame Vibrations
 There are cases where shaft vibrations are
within limits but frame vibrations are
excessive
 Often magnetically induced, with a structural
resonance
 Limit ≤ 2 x allowable bearing housing velocity
for structural member at center line height
Unrestricted © Siemens 2016
Page 18
Revised
Unbalanced Response Test
 Unbalanced coast down from 120% speed
 Mass moment simulator included during testing (option before)
 Vibration levels reduced, e.g.  3600rpm: 2.25mils from 2.74mils
 1800rpm: 2.25mils from 3.87mils
 First critical speed must match predicted results (within 5%)
 If not, correct model
Unrestricted © Siemens 2016
Page 19
Revised
Stator Core Test
 Minimum 30 mins with infrared camera
 Below 5°C change from “adjacent” point
 Packs of laminations and teeth next to each
other or
 Within 6cm (2.2”) when no radial ducts
1
 Record (for comparison purposes) of
 Rated flux
 Watts loss/kg of ‘back iron’
2
1, “Adjacent” core
2, Radial vent
Unrestricted © Siemens 2016
Page 20
Revised
Sample Coil Tests
 Optional tests to verify coil integrity and VPI
process
 Two extra coils VPI’d with stator
 Impulse test
 Ground wall
 5 PU, 1.2 µs
 Turn-to-turn
 2.0 & 3.5 PU 0.1 to 0.2 µs
 Then test to destruction
 Cut coils (3 segments) and examine
Unrestricted © Siemens 2016
Page 21
New
Sample Coil Tests PD
 Concerns about imperfect process causing ‘harmful’ insulation voids
 Partial discharge test on the sample coils that have gone through the VPI process, before surge
tests
 For coils with semi-conductive coating in slot section, energize at rated line-to-neutral voltage
with grounded slot
 Suggested 100 pC PD limit
Unrestricted © Siemens 2016
Page 22
New
TEWAC Heat Exchanger
 Some TEWAC heat exchangers have not performed adequately in the field
 Performance was not required to be verified during factory testing
 Inability to fully load machine at the factory
 Added optional factory test, possibly during factory heat-run
 Verify flow and temperatures per specification
Unrestricted © Siemens 2016
Page 23
New
Stator Coil Data
 Having coil data speeds up rewind as coils can
be ordered before motor gets to shop
 Owner should keep coil data sheet
 Uses the standard coil drawing that coil shops
know
 Can order complete set of coils before motor
arrives
 Gets motor back sooner
Unrestricted © Siemens 2016
Page 24
Datasheet & Guide
API 541 5th Edition
Unrestricted © Siemens 2016
usa.siemens.com/oil-and-gas
INDUCTION MOTOR
API 541 5th Edition -- DATA SHEETS
U.S. CUSTOMARY UNITS
Page 4/4 Motor Supplier Order Data
API 541 5th Edition -- DATA SHEETS
INDUCTION MOTORS
N.A.
1
2
JOB NO.
ITEM / TAG NO.
INDUCTION
HOW TOMOTOR
USE THIS DATA SHEET:
PURCHASE ORDER NO.
API 541 5th Edition -- DATA SHEETS
REQ. / SPEC. NO.
U.S. CUSTOMARY UNITS
Refer to the Data Sheet Guide for comprehensive guidance on all content within this data sheet, which is greatly revised from the
REVISION NO.
DATE
PURCHASER'S SELECTIONS
Instructions
Bold Italics = Indicate Default Selection
INDUCTION MOTOR
API 541 5th Edition -- DATA SHEETS
1
PAGE
ITEM / TAG NO.
REV. DATE
JOB NO.
APPLICATION
PURCHASE ORDER NO.
12
OF
USER
Rev
The Supplier / Vendor and / or Manufacturer is responsible for selections, data and revisions on page 8 - PROPOSAL DATA, where
2 LOCATION
SUPPLIER
REQ. / SPEC. NO.
U.S.
CUSTOMARY UNITS
the Supplier is to provide details about their
offer.







10
11
12
13
14
15
16
17
18
19
20
21
22
23
24





9




































 




12
OF
Rev
ITEM / TAG NO.







 


 





















39
40
41
42








 
 

















 










Inspection & test























































Special Tools Included in Proposal (4.1.11, 8.1.13):
Machine Proposed is in Strict Compliance with API 541 5th Edition? (8.1.9)
 Yes


















 






















































 No  List of Applicable Exceptions Attached





















44 Notes:
44



43
































































38 Magnetic Stator Slot Wedges Used (4.3.10):  Yes
No
40
Liquid Penetrant TestMomentary
(6.2.2.5), Define Parts:




Vertical Pumps:
lbs
Momentary
lbs
Thrust Bearing
Downthrust 39 When Enclosure Pre-Start Purging is specified,
Upthrust
vendor defined maximum allowable pressure (4.4.1.1, e):
Load 41
(4.4.7.1.11,
a)
Hydrostatic
Test (6.2.2.6),
Define Parts:

Continuous
lbs
Continuous

  lbs

40 Low Ambient Temperature Precautions (4.4.10.4):
42 Certified Data Prior to Shipment (8.6.2, a)
Other Information:
 
41 Special Winterizing Requirements (8.1.15):
Other:
43 All Required Test and Inspection Equipment (6.1.4) Provided by Supplier

42 Machine Net Weight (8.1.5):
lbs.







 



Supplier proposal



















Design/As-built





Starting & driven equipment









 





 





 











  
  


 


 




















 


























/

/
/







 


Unrestricted © Siemens 2016






 



 









Page 26






















































  
 













 





 




 
 




Purchaser requirements

8
BY
12
PAGE

Material Inspection (6.2.2)

7
DATE
REV. DATE


6
REVISION NO.
Bold Italics = Indicate Default Selection
PURCHASER'S SELECTIONS
5
REQ. / SPEC. NO.
DATE
BY
Total Copper Weight:
lbs.
Copper Strand Size:
Insulation:
2
11
12
N.A.
REV. DATE
PAGE
OF
Rev
Bold Italics = Indicate Default Selection
3
Number of Strands per Coil Turn:
Number of Turns per Coil:
REVISION
NO.
DATE
BY
AS-DESIGNED
AS-BUILT
3 PROJECT NAME
SUPPLIER REF. No.
JOB NO.
ITEM / TAG NO.
INDUCTION
MOTOR
4
Turn Insulation Description:
2
12
N.A.
REV. DATE
PAGE
OF
Rev
Bold Italics = Indicate Default Selection
PURCHASE
ORDER
NO.
SITE
/
PLANT
NUMBER
of
UNITS
REQUIRED
4
API
541
5th
Edition
-DATA
SHEETS
ACCESSORIES
&
SETTINGS
The Supplier / Vendor and / or Manufacturer shall complete pages 9-12 - MOTOR ORDER DATA, where the AS-DESIGNED symbol
5
Ground-Wall Insulation Description:
BASIC after
DESIGN
- Enclosure, Mounting,
Electrical
REQ. / SPEC. NO.
U.S.
CUSTOMARY UNITS
is to be selected
for initial
DS to
the Purchaser
order
and
the
AS-BUILTsystem
symbol selected
finalNO.
Proposal of thePurchase
As Designed
As
Built placement,
To: transmittal
MOTOR
TAG
No.(s)
5 Applicable
1 Heaters:
Single Voltage Design:
Dual Voltage Design:
JOB
NO.
ITEMfor
/ TAG
INDUCTION
MOTOR
Thickness Turn Insulation:
6
mils 2/4
Thickness
Insulation:
Insulation:
mils
transmittal with
applicable
changes following motor shipment to the Purchaser.
REVISIONGroundwall
NO.
DATE
BY
Page
MotorStrand
Supplier
Order Data mils Thickness
1 any
Enclosure
(4.4.1.2)
PURCHASE ORDER NO.
API 541 5th Edition -- DATA SHEETS
Operating Voltage
kW
Operating Voltages
kW
Sheath Material
Phase
2
Phase
Bold Italics = Indicate the Standard's Default Selection - Refer to Annex C for Data Sheet Guidance
10
12
N.A.
REV. DATE
PAGE
OF
Rev
Bold
Italics
=
Indicate
Default
Selection
7
Coil
Configuration:
Rows
by
Columns
REQ.
/ SPEC.
NO.
U.S.II)CUSTOMARY
UNITS
DPG (Dripproof Guarded) (4.4.1.2.2)
2
WP-II (Weather Protected Type
(4.4.1.2.2)
WP-I (Weather Protected
Type
I) (4.4.1.2.2)
3
Frame Heaters (5.4.1; 5.4.2; 5.4.3):
BASIC DESIGN - General
REVISION NO.
DATE
BY
PURCHASER'S
SELECTIONS
Finished Coil Dimension in Slot, W x H x L (also give tolerances):
8
AS-BUILT
AS-DESIGNED
Provide
filters for WP-I or DPG (5.5.4)
Air Filters:
for WP-II
(5.5.3)
Provisions
Only
for WP-I
DPGcommon
(5.5.2) (same power,
To minimize 3duplication,
a singleRequired
Data Sheet
and set
of requirements
should be
utilized
fororeach
voltage,
JOB NO.
ITEM / TAG NO.
INDUCTION
MOTOR
Main T/Box Heaters:
4
12
N.A.
REV.
DATE
PAGE
Rev
6 etc.)
Applicable
Standardsfor
(1.3.2;
2.0):
North
American
(i.e.,
ANSI,
NEMA)
UseofSIthe
(metric)
dataof
sheets
for
International
Standards
(IEC,3 etc.) OF
Bold
Italics
= Indicate
Default
Selection
enclosure,
rating
intended
the
same
application,
service
or
load,
regardless
number
units.
If
there
are
any
different
Total Number of Stator Slots:
Winding
Throw:
Winding
9
PURCHASE
ORDER NO.
API
541 5th
Edition -- BEARINGS,
DATA SHEETS
HOUSINGS AND
SEALSConnection:
4
Air Filter Capability (5.5.4): 90% of particles > 10 micron
Other:
Bearing Heaters (4.4.8.3):
5
requirements
within /aRPM
service
(e.g.
t/box
locations,
of rotation, etc.),
a separate
SheetSeals
should be used for any unit(s)
7
Power
Ratings
are
Specified
by: direction
User/Project
OEM
BASIC
DESIGNOther
-Data
Bearings,
REQ.Slot
/ SPEC.
NO.
U.S.Side
CUSTOMARY
10
Slot Filler Description
- Thickness:
mils
mils UNITS
Middle
mils
Dimensions:
JOB
NO.
ITEM
/ TAG NO.
1 Bearings:
Type: Top Hydrodynamic
(4.4.7.1.1)
Antifriction
(4.4.7.1.3)
AFBMA Number(s):
Manufacturer: MOTOR
Type:
Model:
5
Purchaser Specified Filters: INDUCTION
with even a single
difference.
REVISION NO.
DATE
BY
Page 1/4 Motor Supplier Order Data
HPSHEETS kW PURCHASE
Motor Speed:
8
Nameplate
Power Horizontal
Rating (4.2.1.1):
RPM (Synchronous)
Machines
1 Bearings:
6 Temperature Detectors:
ORDER NO.
API 541 5th Edition -- DATA
11
Slot Wedge2Material:
Magnetic Slot Wedges:
No
Yes
Split Sleeve (4.4.7.1.1)
Drive End:
Differential Pressure Switch (5.5.5)
6
Differential Pressure Device (5.5.5): Provisions Required for WP-II
Combination
9
12
N.A.
REV. DATE
PAGE
OF
Rev
Bold Italics = Indicate Default Selection
REQ.
/ SPEC.
NO.
U.S. CUSTOMARY
UNITS
9
Nameplate
Voltage/Ph/Hz
Rating (4.2.1.2):
Volts
Phase
Hertz
2 Bearing
Type: Hydrodynamic
(4.4.7.1.1)
Sleeve (4.4.7.1.1)
Tilting
Pad
(4.4.7.1.1)
7 Winding Temperature Detectors (5.2):
RTD-Platinum, 3 Wire, 100 Ohms at 0°C (5.2.1.1) No.per Phase (5.2.1.2): Three (3)
Other
Switch
/
Gauge
12
Stator Bore3Diameter:
Stress Grading Description if Applicable: Opposite Drive End:
Some items may
have an option for 'Supplier Decision'. This
is intended
to give
guidance
direction toPressure
the Supplier
Tilting Pad (4.4.7.1.1)
7
Provisions
Only for
WP-Iclear
or DPG
(5.5.5) and Differential
Gaugewhen
(5.5.5)
BY
REVISION
NO.
DATE
PURCHASER'S
SELECTIONS
o
O
O
AS-BUILT
the Purchaser
has
preference.
10
Minimum
Rated Operating
Ambient Temp.(4.1.2):
Nameplate
Ambient
Temp. Rating (4.3.1.1,b): 40 C Bearing
Other:
3 no other
Constant-Level Oilers
Required
(4.4.7.2.2)
Type:
Other RTD Material:
Wires:
Resistance:AS-DESIGNED
No.per Phase
(5.2.1.2): Three (3)
Other
8
C
C
Special End-Turn
Bracing:
13
Yes
No
4
Hydrodynamic
Bearings: Oil Rings Included (4.4.8.1)
Purchaser Specified Device:
Manufacturer:
Type:DATE
Model:
8
4
12
N.A.
REV.
PAGE
OF
Rev
Bold Italics
= Indicate Default Selection
APPLICATION
1 USER
11
Stator
Class F
Other
Class:(4.4.7.1.3)
4 Insulation Class (4.3.1.1,a):
Antifriction
9
One Common
Lead Each Element Grounded in Box. (5.2.1.2)
14 Other:
5
Bearing, Drive End:
Capable of Self-Lube
Yes
No
Manufacturer
Model / Part No.
or
Use
enclosure
TEFC,in
TEAAC,
or TEAAC
orpage),
higher)
Enclosure
for referred
motors rated
6kV
above:
(4.4.1.1,f):
Each item on9 each page
can be
to by
it'sand
page
number
(in header
the upper
right
of(IP44
each
line number
(down
the selected in line 2
ACCESSORIES
- Main
Terminal
Box
NO. sentences in Data Sheet
ITEM
/ TAG
SUPPLIER
2 LOCATION
INDUCTION
MOTOR
Other:
underlined
Guide
forNO.
this item)
Type:
5page),
Other:
10
Thermocouples:
No.per Phase (5.2.1.2): Three (3)
Other
Stator
Temperature
Rise (4.3.1.1,b)
*: Class
left side12
of each
or Rev.
number
(in header
andBdown
the
right side
of each page). * (SeeJOB
in. Max
in.
Bore Length Strand or Bar Size:
in.
Type
6
BoreTotal
Diameter:
Min Weight:
Other Enclosure:
10
(4.4.1.2.3)
TEPV (4.4.1.2.3)
15 Rotor Information:
Conductor
lbs. Number of Bars:
Box
Minimum--sizeDATA
is per NEMA
MG 1-20 Type
II with Copper
BusNO.
Bar & Standoff Insulators Required
1TEFC
Main
Terminal Box (5.1.1):
PURCHASE
ORDER
API
541Size:
5th Edition
SHEETS
SUPPLIER REF. No.
13
Duty (4.1.2): Continuous
Other:
Other 3 PROJECT NAME
11
Vertical Machines
in.
Max
in.
Bearing
Loading:
PSI
7
Design
Clearance
with
Shaft:
Min
11 6 Bearings:
Aluminum
Alum.
Alloy
Copper
Copper
Alloy
Other
16
Conductor
Material:
Ring
Material:
Retaining
Ring
Alloy,
If
Applicable:
REQ.
/
SPEC.
NO.
U.S.
CUSTOMARY
UNITS
2 Instructions
Other Size:
Supplier
Std.for
Req'd.Accessories
For Shielded
Cable Term.(5.1.6,
e)
Other:
Heat
Exchanger
Tube
on
how
use
sheet symbols
topower
make
selections
TEAAC
(4.4.1.2.3)
Other:
NUMBER of UNITS REQUIRED
4 SITESettings:
/ PLANT Alarm:
14
Max. Sound
Pressure
Level @
1 m.
@ noto
load,
full data
voltage/frequency
on sine wave
(4.1.3;
4.1.4): 85 dBA
dBA
12
Recommended
Shutdown:
Materials
(4.4.10.8,
a):
Momentary
lbs
Momentary
lbsBY
REVISION NO.
DATE req'd for offshore)
PURCHASER'S
SELECTIONS
Thrust
Bearing
12 7 3
SteelRight
300 Series
Stainless
316 Series
(4.4.10.8,
17
Shaft 8
Material:
Ring of
Dimensions
Thermal Insulation (5.1.6, a)
Box Location
facing
non-drive Downthrust
end:
LeftStainless
Side
Side
Other: Steel
Bearing, Non-Drive End: Capable
Self-Lube Premachining:
Yes
No
Manufacturer
Model / Part No.
Upthrust
5
MOTOR Other
TAG No.(s)
Voltage and
Variations
(4.2.1.3):
Per NEMA
Other:
Load
(4.4.7.1.11,
a)Bold
5
12
OF
Rev
N.A.Frequency
REV.
DATE by a solid
Some of15the paragraphs
in the Standard
require
a Purchaser
Decision
or
are Selection
Optional. These arelbs
indicated
round bulletPAGE
Italics
= Indicate
Default
Bearing
Temperature
Detectors
(5.3):
One
(1)
Per
Bearing
Hydrodynamic,
Thrust
Bearings
Qty
/
Bearing
Dual
Element
13
8
Continuous
Continuous
lbs
Other
13
(4.4.1.2.4)
Heat
Exchanger Bottom
Tube Materials
b):End
90-10
4TEWAC
Cable
Enter From
(5.1.4.1):
End
Side
Quick Disconnect
Studs or Receptacles (5.1.6,f)
SideCu-Ni
Top(4.4.10.8,
in. Max
in.
Bore Length
in.
Type
9
Bore Diameter: Min
next to the
in the
Standard.
This
data
sheet usesASD
openPower
bullets
to Drive
identify
those
items Non-Drive
thatSolid
fit this
convention.
18 Notes:
16 paragraph
Motor Power
Source:
Sine Wave
Power
(complete
below
section)
State
Soft StarterChanging
- Completethe
data on page 6, line 8
ACCESSORIES
MOTOR
RATING
PERFORMANCE
DATA
14
Provisions
Only - ELECTRICAL
Install perAND
API 670
(5.3.1)
Ground One Common Lead
RTD - Platinum, 3 Wire, 100 Ohms at 0°C (5.3.1)
9
Other:
14 bullet
WaterConductor
Conditions
per 4.4.1.2.4,
a: Type
Water & glycol
solution
water conditions (attach
documentation)
bullet to a solid
on Incoming
the
data
sheet
indicates
the Purchaser
requires
an item
or that the item appliesOther
to
thecooling
Purchaser's
Qty.
Per
Phase
Provision
for Purging (5.1.6, c)
Insulation
5 Cooling
Size:
in. Max
in.
Bearing Loading:
PSI
10
Design Clearance with Shaft:
Min
19
17
Adjustable
Drive (ASD)Frame
Conditions,
if applicable
(4.1.4;5.4.2;
4.1.5;5.4.3):
4.2.1.2.3,
4.3.1.2):
1Speed
Heaters:
Space
Heaters (5.4.1;
Sheath
Material:
Supplier Decision
Other:
requirements
for
the machine.
Frame Size / Designation
6 Material:
Quantity
Type Wires:
/ Model No.
Utility-Grid
ASD
Other RTD
Other info: Motor Power:
15
Resistance:
15 10 Seals:
Location-orientation
(4.4.1.2.4,
c): (4.4.7.3.a)
Supplier750kW
Decision
Stator(4.4.7.3,
Other
Special
for
Gas
Purge
Non-conducting
Seals
b)
6 Cooler
All Phase
Leads Seals
In Terminal
Box
(4.3.6):
Required
(1000HP)Above
and larger
Removable Links (5.1.6, d)
Provide
in < 750kW (1000HP)
11
Special
Seals
for
Gas
Purge
(4.4.7.3,
a)
Non-conducting
Seals
(4.4.7.3,
b)
Other
Seal
Type
20
ASD 2
only operation (4.2.4.5)
ASD+DOL
StartDesign
capability Operating
ASDVoltage
only w-Bypass to Utility Power
ASDPhase
w-DOL Start & Bypass to Utility
18
Single Voltage
RPM Full Load
HP
kW
RPM Synchronous
7 Nameplate
Poles
Type: Power / RPM Rating (4.2.1.1):
16
Thermocouples:
16
location
Supplier
Decision
Right
Side
LeftNone
Side
OnInlet-Outlet
lineBus
5, select
the
applicable
bullet
to indicate
the
status
of the data
sheet.
TheTin
initial state
is 'Proposal',Other
andCopper
it should
Copper
Joint
Plating
(5.1.6,NDE):
i):
Supplier
Decision
Ground Bus (5.1.6, k)
7 Cooler
Silver
or(facing
11 Other:
Thrust
Bearing:
Antifriction
(4.4.7.1.5)
Hydrodynamic
(4.4.7.1.10)
Bearing
Loading:
PSI
12
21
19Page 1
Variable
Torque
Speed
Range:
Min
Speed
RPM
ft-lb
Max.
Speed
RPM
ft-lb
Phase
3 be changed to 'Purchase' to indicate
Dual Voltage
Operating
Nameplate Voltage/Ph/Hz
Volts (4.2.1.2)Alarm Contacts Number
Phaseof Contacts
Hertz
a finalDesign
revision and
purchaseVoltages
of the machine is underway.
NO
NC
17
Dial Type8 Thermometers
(4.4.7.1.16): Rating
Type (4.2.1.2):
/ Bus Bar between
JOB NO.
ITEM / TAG NO.
MOTOR
17
Tube Construction
(4.4.1.2.4, d;
c):
Single
Tube
Double
Tube
Redundant
Coolers (4.4.1.2.4,
b) INDUCTION
6kV &
up use Insulated
Stator Windings
and Main Terminals (4.3.9)
Insulated Terminations
and4.4.10.8,
Interior Jumpers
(5.1.6.m)
12 8
Thrust Bearing
13
Momentary
lbs
Momentary
lbs
22
20
Constant
Torque Speed Range:
Min
Speed(4.4.8.3):
RPM
Max. Speed
RPM
ft-lb
PURCHASE ORDER NO.
API
541
5th
Edition
-DATA
SHEETS
4
Bearing
Heaters
Operating
Voltage
Phase
9
Insulation
Class
(4.3.1.1,a):
Temperature
Rise
(4.3.1.1,
b):
Class
B
Enclosure
(4.4.1.2):
Class
F
JOB
NO.
ITEM
/
TAG
NO.
INDUCTION
MOTOR
18
Antifriction bearings:
Above
selectionsDownthrust
applied to Antifriction bearings
Pages
these
pages,
and change
to solidTube
theSingle
bullets
that
apply
to the
Purchaser's
requirements.
Upthrust
Load
Capability
Coolers:
Inner
Tube
Leak
Detection
Required
Outer Tube Detection also
181 - 6 9 LeakThroughout
Detection
(4.4.1.2.4,
c): select
Required
Phase
Main T/Box
Space
Heaters
(5.1.6,
b):For Double
Voltage
Design
Operating
Voltage
REQ. /SHEETS
SPEC. NO.
U.S. CUSTOMARY
UNITS
DESIGN
- Bearing
PURCHASE ORDER NO.
14
Continuous
23
API 541
5th Edition -- DATA
21
Constant
Max Speed
RPM
ft-lbLubrication
or BASIC
(4.4.7.1.11)
5 Power Speed Range:
Main Terminal
Box Space Heaters
required:
also
see Main
Terminal Box section, page 4
Pull-Up Continuous
(PUT)
Breakdown (BDT) lbs
10 Full-Load
Torque
(FLT)
ft-lb
Percent FLTShutdown:
at: Locked-Rotor (LRT) lbs
19
Recommended
Settings:
Alarm:
JOB NO.
ITEM / TAG NO.
INDUCTION MOTOR
Referand
to
page
5 for
T-Code,
Norm.Open
Norm.Closed
19
Sensor
with
Local
Indicator
(4.4.1.2.4,
g): apply
Required
Not requirements
Required
Relay
Contacts:and Testing
change
to heater
solid the
bulletsetc.
that
to the Purchaser's
for Analysis,
Inspection
Operating
Voltages
Dual Voltage
Design
10 FlowSelect
Phase
/as
BY
PURCHASER'S
SELECTIONS
REQ. DATE
/ SPEC. NO.
U.S. CUSTOMARYREVISION
UNITS NO.
13 Description
Hydrodynamic
Bearings:
Ring Type
Self
Lubrication
(4.4.8.1)
15
Non-Drive
Endfollowing
Drive
EndManufacturer
Model / Part No.
24
22
ASD
and
Information
affecting
motor
design
(Obtain
from
Supplier;
Data
Sheet
Guide)ifrequires
For
Classified
Areas
provide
PURCHASE ORDER NO.
API 541 5th Edition -- DATA SHEETS
above.
Additionally,
change
theCode
triangle
bullet
toASD
a solid
triangle
onlytowhen
the
Purchaser
all units of a
6 described
Temp.
(from
pg.1):
T3refer
used
for
labeled
heaters
not specified
at the
Loads
(100% Voltage):
11 Expected Data (8.1.3,f)
20 Enclosure Accessories
Page
6 DATEOF
12
Purchaser
Specified
Device:
Manufacturer:
Type: N.A.
Model:
20 7
PAGE
REV. DATE
Rev BY
REVISION NO.
PURCHASER'S
SELECTIONS
Bold
Italics
=
Indicate
Default
Selection
Temp.
Code
and/or
Max.
Surface
multi-unit
order
to
receive
the applicable
inspection
orSupplier
test.
Leaving
the
triangle
bullet
indicates
the inspection
11type
and Installorby Supplier : o
For
the devices
following
below,
the Purchaser
may make
a Provide-Install
selection;
theopen
default
is Provide
REQ. / SPEC. NO.
U.S. CUSTOMARY UNITS
o
14
Type/Viscosity
of Oil
(4.4.8.5;
4.4.8.8;
5.1.4.2)
Decision
Other,
Define:
25
23
ASD
topology:
LUBRICATION
SYSTEM
75%
100%
Locked-Rotor
50%
7 /test
Max.
Surface
Temp.:
Temp. (5.4.2):
12
Load
Point:
Other:
%
Data
is:
C
(less
than
or
equal
to
80%
of
AIT
on
pg.1
for
unlabeled
heaters,
160
C
if
AIT
not
specified)
7
12
REV. DATE
OF
Rev
PAGE
Bold Italics
= Indicate Default
Selection CONDITIONS
to one
unit of a multi-unit
order.
WP-II,
WP-I, DPG/ODP (4.4.1.2.2)
Air Filters:
Provided (5.5.4): Required for WP-II (5.5.3)
Air Filters Not Provided (5.5.4)
21
Cooler Airapplies
Inlet &only
Outlet
Temperature
Sensor (4.4.1.2.4,
h):
Required
Not Required
Same as WindingN.A. Other
21
REQUIREMENTS
AND STARTING
REVISION NO.
DATE
BY
MOTOR PROPOSAL DATA
and
InstalledLOAD
By
12Output
DifferentialLube
Protection
Current
Transformers
(5.1.6,Common
h; 5.1.8; With
5.6.3)
Driven Equipment (4.4.8.5) Provided By
Pressurized
Required
(4.4.8.4)
15
26
24
ASD
Harmonics,
describe
and/or
attach
data (4.3.1.2):
16
Hydrodynamic
Bearing Ring Type Self Lubrication
(4.4.8.1)
Constant-Level
Oilers (4.4.7.2.2)
%
%
% Provisions Only
13
Efficiency:
%
Calculated
Supplier,
Vendor and/or
Manufacturer
to complete
this 3page,
the bullets
to indicate
items applicable
to
their
ANALYSIS,
SHOP
INSPECTION,Selection
AND TESTS
8 The
Winding
Temperature
Detectors
(5.2): isRTD
Other
RTD
Material:
- Platinum,
Wire,using
100 Ohms
at 32°F
(5.2.1.1)
12
PAGE
OFCapability
Other
Air Filter
(5.5.2)
22 8
Filter
(5.5.4):Rev
90% of particles%
> 10 micron
22 8
Purchaser
Specified
Device:
Manufacturer:
Type:
Model:
= Indicate
Page
Per NEMA MG 1-20
orBold Italics
Per
specifiedDefault
load curve & data (4.2.2.1,a) REV. DATE
1 Load Torque and Inertia
Requirements (4.2.2): N.A.
13Maximum
Type:
Self-balancing
Full
Differential
offer.
System
Supplied
By
(4.4.8.4):and Rise-Time
Other
Driven
Supplier
Motor@Supplier
16
27
25
ASD
Voltage
Spike
Amplitude
atEquipment
drive output
(4.3.1.2.1): End User
Volts
microseconds
Pressurized
Lube (4.4.8.1, 4.4.8.4)Oil
Rings Provided:
Yes
to operate without
Yes Tested
No Unit
17
% lube system: Previously
%
%
%No Bearings designed
%
14
Power Factor:
9 TheEnclosure
Other
Wires:
Resistance:
Required
Number
per(4.4.1.2.1)
Phase
(5.2.1.2):
Three
(3)applicable
Indicates line item is not required
( v ) Indicates lineMOTOR
item applies
to only one
machine in a multiple
machineDATA
application/order
1 (4.4.1.2.1)
( m ) IC
 Loaded
23
Filter Manufacturer:
Type:
Model:
SUPPLIER
/ Partially
MANUFACTURER
PROPOSAL
of the
Protection
(4.4.1.2.1)
IP
Method
ofOrder
Cooling
23
Alternate
Identification
Supplier,
Vendor
and/or
Manufacturer
isDegree
to select
bullet to indicate
the
status
of the
Motor
Data
Design
Load
Curve
Condition:
Unloaded
(e.g.
closed
valve
or
damper)
(e.g.
open
valve
or
damper)
2
Loaded
(e.g.
min.flow)
Ratio
14Maximum
Accuracy
Class
Quantity:
17
Lube
System
to comply
with
API
614
(4.4.8.6):
Part
3 General
Purpose
Partwhen
2: Special
Purppose
ISO 10438-1
28
26
ASD
Common
Mode
Voltage
(CMV)
atplaced.
drive output
(4.3.1.2.2):
Volts
section
sheet
after
an
order
has
been
Above
line
1,
the
As-Designed
bullet
is
selected
pages
9-12
have
Other
18
Common
with
Driven
Equipt.
(4.4.8.4)
System
Supplied
By
(4.4.8.4):
Driven
Equipt.
Supplier
End
User
Motor
Supplier
15
Current:
Amps
Amps
Amps
Amps
Amps
Tested
this Order
10 of Units
Ground
One (1) Common
in terminal
box (5.2.1.2)
required line item  ( t ) Indicates line item applies
to all machines in a multiple machine application/order
2
( l ) Indicates Purchaser
SI (Metric)
24
System
for Hardware
(1.3.1): Lead Each
U.S. Element
/ North American
Customary
Frame Size / Designation
Provisions Only Provided
Device Not Provided
24
Differential Pressure Device (5.5.5): Provisions Required for WP-II
3
Load The
Re-acceleration
Required
(4.2.2.1, b): NO 1 Manufacturer
Yes
Re-acceleration Load Data or Curve No.:Type / Model No.
completed
and(5.1.6,
are returned
to the5.6.2.3):
Purchaser during the initial transmittal of documentation.
As-Built bullet
is
15 ASDbeen
Surge
18
Main
OilCapacitors
Pump
Driven
by: g; 5.6.2.1,
Supplier DecisionMicrofarads
Separate, independent motor
Main motor shaft
29
27
Other
information
/ motor
requirements:
19
Only Lube
System (8.1.3,f)Required / Recommended
of Oil (4.4.8.5; 4.4.8.8):
16 Motor
Guaranteed
Efficiency
% Efficiency atType/Viscosity
% Load
Efficiency Determination Test Method (8.1.3,f):
Type:
11 selected
Thermocouples:
No. Series
perversion
phase:
(3)forMake
Other
Pages259 - 12 Hardware-Fasteners
to indicate
the (4.4.1.1.c):
final
configuration
of the motor(s)
including
changes
since the As-Designed
selections
inQty.
only one column for each item HP
Required
Witnessed
ObservedVolts
3 ofThree
Material
Stainless
Steel 300
Series any
through
M12made
(1/2 in.)
SS
316
through
1/2
in.
offshore
Poles
RPM
(Synch.)
Phase
Hz
2
Differential Pressure Gauge Provided (5.5.5)
Combination Switch / Gauge Provided
25
Differential Pressure Switch Provided (5.5.5):
Seconds
4
If Yes Above, Complete the Following (4.2.3.5):
Max Time of Voltage Interruption
kVthe
Rated
Surge
Arresters
(5.1.6,
g; 5.6.2.2,
the
dataLube
sheets
were
transmitted.
This5.6.2.3):
final version of
data sheet is transmitted to the Purchaser after the applicable
19 16
Other
System
information:
30
28
20
Oil Requirements
(8.1.4):
Heat Loss
To Be Removed
per Bearing
kW
% Efficiency atGPM
17 Total
For Bearing
Reciprocating
Loads (8.1.3,f)
% Load with PSI % Current
Pulsation
Max. Current
Variation (8.1.3,g):
A
4
(6.1.3.3;
6.1.3.1; 6.3.1.1)
(6.1.3; 6.1.3.2;
Provision
for Pre-Start
Purging
(4.4.1.1,
e):(5.3):
Purchaser
Specified
Purgethroughout
Details:
26
Class B6.3.1.1) Service
3 Voltage
Temperature
Rise
Full Load
SpeedTerminals during re-acceleration
RPM Insulation
Class 6.3.1)
1.0 Manufacturer:
12 motor(s)
Bearing
Temperature
Detectors
Onethe
(1)other
Per Bearing
Hydrodynamic,
Qty / to
Bearing
Dual Element
OK
F Volts(6.1.3;
been
shipped.
The
uses
bullets
pagesThrust
9-125toBearings
indicate itemsOther
applicable
26 Factor
Device
Type:
Model:
at Motor
17
Currenthave
Transformers
(5.1.6,
h) Vendor
for Phase
Meter
20 Classification
Cleanliness
Requirements
of Classified
APICurrent
614offor
5 motor.
GPM
& above capacity
(6.2.3.2)
31
21
Motor
for Supplemental
Mist (4.4.7.4.1)
Other Lube System
information:
or Zone
Forprepared
Motors
Operating
on ASD Purge
PowerOil
(8.1.3,f):
Base Frequency(ies)
and Harmonics
assumed in the supply waveform(s) (8.1.3,f):
18
29
Nonclassified
as:
Class
Group
Division
Area
(4.1.8):
either Meet
the
As-Designed
or
As-Built configuration
the
2
2
Field
Sizes 3(4.4.3.1):
Supplier
Std.(5.3.1) Other: Provisions Only
27
Full-Load Torque (FLT)
ft-lb Rotor Inertia (8.1.3, c)
13 Piping Connection
RTD - Platinum,
Wire,
Install per API 670 (5.3.1) 5 Coordination
Ground One
(1) Common
Lead
100 Ohms
at 0°C
lb-ft227 WkRecommended
GR2
GD
Meeting
(8.2)4 Enclosure
settings for Differential Pressure Switch: Alarm:
Shut-Down:
Ratio
Accuracy
Class
18
Quantity:
6
Motor
Starting
(4.2.3):
Across-The-Line
Starting
at
80%
of
Rated
Voltage
(4.2.3.1)
or
Other
ATL
%
of
rated
voltage
%
21
Purge Oil Mist (4.4.7.4.1) (describe or attach
requirements):
32
o
Speed-Current
Speed-Power Factor
19
Curve No.'s
(8.1.3,a,b): Grease
Speed-Torque
30
Temperature
Code (T-code):
Autoignition Temperature (AIT):
C
BULLET
ITEMS
NOT
SELECTED
ARE
CONSIDERED
NOT APPLICABLE,
Type:
22
Antifriction
Bearings:
28
Duct
Provided
by (4.4.3.8):
Supplier
Std.
Other: Resistance:
5 Locked-Rotor Torque (LRT)
% FLT
% FLT
Breakdown Torque (BDT)
%
FLT
Pull-Up Torque (PUT)
14Gaskets/Bolts
Other RTD
Material:
Wires:
Other
info: Review (8.4)
6
Design
Fuses Required
19
Voltage Transformers (5.1.6, j) for Voltage Meter
TEAAC Enclosure (4.4.1.2.3) Heat Exchanger Tube Materials (4.4.10.8, a):
28
7
Other Starting Method (4.2.3.2, a):
Autotransformer
Captive Transormer
Reactor
Solid State Soft Starter
ASD
33
ORBearings:
WILL FOLLOW
THE
DEFAULT
CONDITION
WHERE
Acceleration Curve No.
20
When
No.Oil
(8.6.2,b):
31
Grease
Type:
Supplier
Decision
Other IT EXISTS
22 Other:
Antifriction
23
Pure Oil
Mistspecified:
(4.4.7.4.5)Calculated Rotor-Response
Oil Mist Ready Curve
or
Mist Provisions Only
29
Auxiliary
motor
driven fans (4.4.10.6.3):
Yes
No
Ph / Volts.:
phase
For Recip. Comp., Calc. Eff. is based on Pulsating Current Conditions
from Pg.6
6 Calculated
Type:
15
Thermocouples:
Lateral Critical Speed Analysis
(4.4.6.2.1; Expected
8.6.2, b) Data (8.1.3, f) at the following Loads:
7Volts
Ratio
20
Accuracy Class
Quantity:
29
TEWAC Enclosure
(4.4.1.2.4)
Heat
Exchanger
b):
90-10
Cu-Ni StartingOther
8 Only (bearing
Other Method
%
volts:O may be required
% - see
If Soft
Starter, define Percent Locked Rotor Current Limit during acceleration:
%
34
O
21 Acceleration
Time
(8.1.3,d):
At Tube
RatedMaterials
Voltage: (4.4.10.8,sec.
Minimum
Voltage/MVA:
At Yes % Voltage
Sec
sec.
23 Data (4.1.2;
Pure4.4.8.3;
Oil Mist 4.4.10.4):
(4.4.7.4.1; 4.4.7.4.5)
Oil
Mist Ready or
Oil
Mist Provisions
grease
removal
guide)
No
24
GreaseAt
removal
required before
operation with oil mist?
32 30Site
Max
SiteThermometers)
Ambient
Temperature:
CTorsional
75%
100%
Area Classification (4.1.8):
Paint
Paint System
Purchaser
Specified Paint
System
Paint SystemMin
Specification:
7 Load
Point
Other:
%
Alarm
ContactsF Number
Contacts:Analysis DataNO
16 System:
OilSupplier's
Temp. Indicators
(Dial
(4.4.7.1.16)
Type:
NC
8 of
(4.4.6.2.2)
Analysis By:50%
21
Partial Discharge (PD) Detectors (5.6.4.1, 5.1.6, l)
30
Tube Construction
(4.4.1.2.4,
d; 4.4.10.8,
b,c):No. (4.2.4.2)
Single Tube
Double Tube
35
Maximum
Locked
Rotor
Current
other
than
in
4.2.4.4,
a
(450
to
650%):
%
of
Full
Load
Amps
or
Maximum
Amps
9
O
22 Thermal
Capacity
/ Limit Curve
Instructions
on
how
to change
data
sheet
symbolsSupplier
to
selections
Rotor Inertia - Wk2 (8.1.3,c)
lb-ft2
33 31 Minimum
Rated
Storage
Ambient
Temp.(4.1.2):
Sitemake
Elevation:
ft. Code:
CSpecified
24 Vertical
Motor
Bearings:
Thrust
Bearing:
Supplier
Decision
Grease
Lubrication
Oil
Sump
Paint
Color:
Supplier's
Paint
Colorfor
Purchaser
Define
Paint Color
and
Nonclassified
Classified25
as: ClassVertical Motor Bearings:
8 Acceptance
Efficiency
% Before Tests (6.3.1.4)
%
%
%
17
Location
of
Terminations
Bearing Temp.
Det.
(5.1.14): Paint Color
Decision
Terminal
HeadLubrication
T-box
T-box
with
Winding and
Temp.
Det.
Thrust Bearing:
Guide Bearing:
Mfgr. Recommended Lubricant:
9
Submit
Test
Procedures
Criteria
6
Weeks
22
Describe Required System:
Tubes
Only
Outer
also at
31
Leak
DetectionWithstand
(4.4.1.2.4,Time,
c): Required
Double at
Tube
Leak
Detection: Inner
36
Min.
at
Motor
Terminals
under
Amps
Locked
Rotor
Current
10
Determine
Starting
Capability
per
(4.2.3.2,
b):
Volts
(4.2.4.2,a;
8.1.3,e)
100%
Voltage
Sec
%
Voltage
23
Locked-Rotor
Cold
at
80%
Voltage
Sec
Sec
1) Select (click
on)
symbol
34
Relative Humidity:
% Bearing:
Max
% Decision
Min
Use Higher
Elevation for motor rating:
ft.
Guide
Supplier
Other:
or Zone
Factor(6.3.1.15)
%
%
Group
18
Antifriction
bearings:
Use selections
above
when Antifriction
bearings
26
Oil Sump Lubrication
Oil Sump Lubrication
Type/Viscosity of Oil
10 Demonstrate
Accuracy of 9TestPower
Equipment
%
%
 Division
32 25
Mounting:
Horizontal
Foot
Mounted
Horizontal
Flange
with
Feet are specified
Vertical
23
Vertical Outside
Surface
ofMounted
Main T-Box
PD T-Box
location
(5.6.4.3):
Other:Foot Mounted
(4.4.1.2.4,
b)
32
Cooler Location/Orientation
(4.4.1.2.4, Time,
c):
37
S.C. MVA and
11
or (4.2.3.2,
c):
X/R ratio with
base voltage and
% Rated Volts at Motor Terminals
Type listedControlled:
letter on keyboard
O
O Min.
24 Locked-Rotor Withstand
Hot (4.2.4.2,b; 8.1.3,e) at 100% Voltage
Sec at 80% Voltage Redundant
Sec Coolers
at
% Voltage
Sec
o
35
Motor Location:
Indoor Building2)
Temperature
No
Yes Controlled Temp.:
forCore
motorTest
rating
F
C Non-Reverse
Amps
Amps
10 Current
27
Grease Lubrication
Grease Lubrication
Grease Type:
C or Temp.Code
11 Use
Stator
 Amps
Amps Autoignition Temp

Shaft Up
Solid Shaft
Hollow Shaft
Ratchet (6.3.4.1)
33 26 Other:
Vertical
Flange(5.8)
Mounted
Shaft Down
19 Vibration
Detectors
Max
Min
Water
Pressure
(PSI):
Max
Min
33
Water
Flow
(GPM):
38
MISCELLANEOUS,
SUPPLIER'S
DATA
3) Press enter or click onto next item
12
Other:
% Volts
Other:
Provide Curves & Data (8.1.3, a, b): at Rated Voltage & Min.Start Conditions
Consecutive Successful Starts With :
Locked-Rotor Current at 100 % Voltage
25 Starting Capability (4.2.4.1):
Amps
36
Outdoor
Roof Over Motor:
No
Yes
Offshore Platform / similar marine 12
environment
(4.4.1.1.c) Test11 - required
Guaranteed
Efficiencies
(8.1.3, f) at
% Load =
% Test Method (8.1.3, f):
Surgepg.
Comparison
for all machines
(6.3.4.2)
34
Vertical Motor
to
carry thrust
(if selected,
complete
applicable
area
Bearing
&/or Driven Equipment
/ OEM section,
6, lines 39-40)
VIBRATION DETECTORS
SPECIAL
CONDITIONS
Motors
operating
at 1200
rpm of
and
higher
Motors
operating
at Other
less than
Non-contact
Shaft
Probes
Only temperature
34
Flow26Sensor Local Indicator Provided (4.4.1.2.4, g) Motor Provisions
39
To change:
your
Keyboard
and
enter:(5.8.1):
24 20Use
Qty.
Special
Tools
and
Lifting
Devices (4.1.11,
4.1.12,
4.4.2.14):
Proof
of of
Nonsparking,
Corrosion-Resistant
Fan rpm
(4.4.10.6.1)
13
No.
Consecutive
Starts
than1200
Table
3 (4.2.4.1): With motor temperature at ambient: 3
Other:
Description
Manufacturer:
Type:
Model:
80
%
Voltage
initially
at
ambient
3
Locked-Rotor
Current
at
Amps
Importance Factor:
37
Seismic Loading (4.4.2.2), IBC Zone:
Other Seismic Requirements:
12 (6.3.4.2.1)
Max. Sound Pressure Level (4.1.3) 85 dBA @ 1 m. NO-LOAD, 
FULL VOLTAGE/FREQUENCY,
SINE WAVE POWER
Other:
dBA Shaft Probes (5.8.1): Number per bearing: TWO (2) (5.8.1)
13 Special Surge Test of Coils


Other:
35 27
Flange
Type
/ Bolt
Circle:for 4 or Supplier
Decision
28
Non-contact
Four (4) (5.8.2)
and
Spider
one
piece
forging
more poles
4.4.5.1.2,
b)
Shaft
Probes
(X-Y)
(5.8.1):
Installed
Provisions
Installed
35
Relay
Contacts
Provided:
Normally
Open
Normally
Closed temperature 2
40
25 21ShaftSeparate
Nameplate
-(4.4.5.1.4;
listitem
below
(4.4.11.4)
Electronic
Vibration
Test
Datamotor
- Define
Digital Format
below
Provisions
14 to an
Other:
to
Changes
an
from
default or not required
item that
isWith
required
temperature
greater
than(6.3.3.17)
ambient but less than rated operating temp.: 2
27
Motor
temperature
above ambient
but not
exceeding
rated operating
Locked-Rotor Current at
% Voltage
Amps
lower
case " l with
" Purchaser's Information
14 Power Factor Tip-Up Test
38 36Unusual Site Conditions,
Define:

 only w-Bypass to UtilityPower
Other
Mounting
Requirements:
required
Provisions
Installed
Manufacturer:
Model:
29
Shaft Probes:
13(6.3.4.3)
Motor Power Source: Sine Wave Power
ASD Power only
ASD
28 26 22SpecialPhase
Lower
Vibration
Limits,
Define
Installed
Provisions
Installed
Reference-Probe
(5.8.1):(6.3.3.12):
Flow
Shutdown
Set Point
GPM With Motor Stopped
36
HighWait
Flowtime
Alarm
SetallPoint
GPM
41
No.of Full Voltage Starts if more than 5000 required (4.2.4.1; 4.4.5.1.1):
15
With
Motor Running
Sec
Sec
28
after
Consecutive Starts have
been used (4.2.4.2,Low
d, e):
to39 37
an item from beingSoleplate:
required to
the default
or
not required
lower case
"m"
15 Stator Inspection Prior to14
VPI (6.3.4.5)
Additional
Environment
Considerations,
Chemicals,Changes
etc. (4.1.2):



Baseplate:
Furnished
By
(4.4.2.6):
Furnished
By
(4.4.2.6):
Provisions
Installed
Manufacturer:
Model:
Phase Reference Probe (5.8.1):
ASD + DOL Start capability
ASD w-DOL Start and Bypass to Utility Power 30
Two cost
(2) / kW
Two at
(2)
29
Evaluation
Factor(X-Y)
(8.1.2),
EF =
C
= (4)
cost / KWH
applied
23Efficiency
Number
per bearing
(5.8.2):
Four
Four%
(4)of full load
Cooler
InletSound
& Outlet
Temperature
h):@
Required
37
42
Type:
Model:
85 dBA
29 AirMax.
Pressure
LevelSensor
(4.1.3) (4.4.1.2.4,
1 m., no-load Manufacturer:
Other:
Other:
Special Shipping Bearings16
(6.4.1,
k)
Outdoor Storage More Than Six Months (6.4.2)
27 Packaging (6.4.1)
Domestic
Export Boxing
Changes
an Inspection or Test from applying to one unit only to applying
16to Sealed Winding Conformance
TestVariable
(6.3.4.4)Torque Speed Range: Min Speed
40 38
Abrasive Dust Protection,
Open
Enclosures
(4.4.1.2.2,c):
RPM


Foundation
applies
(4.4.6.1.3,
4.4.6.2.1.1),
Description
Provisions
Installed
Manufacturer:
Model:
31
Oscillator-Demodulators:
15
ft-lb
Max. Speed
RPM
ft-lb
to
30 Non-massive
for case
Expected
Guaranteed
Efficiency
Data (8.1.3.f):thrust bearings at the thrust end (5.8.2):
lower
" (2)
t "and
Provide
two
axial-position
probes
for hydrodynamic
Provisions
Installed
24Test Method
38
Sensor Type:
ALL machines
of a multi-unit
order. Purchaser defined Efficiency Method (8.1.3,f):
DRIVEN
EQUIPMENT
INFORMATION
OEM
DATA
Ohms,
@
°F
30
Induction
Motor
Equivalent
Circuit
Data:
Phase-to-Phase
Resistance
Typical
Drawings
&
Literature
with
Proposal
(8.1.8)
28
Proposals
(8.1)
17 Partial Discharge Test for16Machines
6kV andTorque
Greater
(6.3.4.6)
41 39
Corrosive
Agents in Environment,
re: stress
corrosion
cracking (4.4.10.1.2):
RPM


for Non-massive
System
Dynamic
Analysis
Required
Machine or
Vendor
per 4.4.6.1.3,
a, ALL
b, c,machines
d
Constant
Speed
Range: Min Speed
Max. Speed
RPM
ft-lb
ChangesFrom
an
Inspection
Test from
applying to
of a multi-unit
31 Data
Codes,
Define
(4.1.8):
25Local
Probe lead
protection
(5.8.1.1):
Conduit
Other:
Bearing
Seismic
Sensors
Per
API 670 (5.8.3)
32 Cooling
Water/Glycol
Solution
Other Cooling Water Conditions (Purchaser Specified)
39
WaterHousing
Conditions
per 4.4.1.2.4,
a (5.8.3):
to
lowerPrice
caseFor" Each
v " Test on Data Sheet
31
kVA Base at Rated Voltage and 77°F Subtransient Reactance X"d
Total Winding Capacitance to Ground
uF
29
Separate
(8.1.14)
Price
For
Tests
on
Data SheetTag
(8.1.14)
17All Driven
Equipment:
No.(s):
Description
Location
order
toVolts
applying to Phase
onlyPackaged
one unit of
a Hertz
multi-unit
order.
Rotor Residual Unbalance
Test (4.4.6.3.4)
18
42 40 Other:


RPM
Maximum
Ground Fault
Amps 17Verification
Electrical
System:
Primary
Source
Constant
Power Speed Range: Max Speed
ft-lb
32
Loads
Imposed
on Motor
Enclosure when Connected
at Installation
Site, Define
(4.4.4):Defined,
Avoiding lateral natural frequencies 33
by at least 15%Sensor:
not
26External
Manufacturer
ofPower
Probe,
Oscillator-Demodulator:
Supplier
Decision
Purchaser
Type:
Provisions
Installed Type:
Manufacturer:
Model:
40 When Enclosure
Purging
is Rated
specified,
Supplier defined
max.
e): R
Magn R
32 Pre-Start
Locked
Rotor at
Voltage:
Stator
R allowable pressure (4.4.1.1, Rotor
30
Provide requirements for Special Weather & Winterizing Protection (8.1.15)
stall timeMfgr.:
calculation
method and
limits (4.2.4.3)
Type / Model
No. to select one of below options)
RPM
18 Provide
Drivensafe
Equipment
practical over specified
speed range (4.4.6.1.2)
19 Unbalance
Response
Test
(Purchaser
43 41 Method



of System
Grounding
(5.6.2.3)
Resistance
Reactance
Ungrounded
Solid
18 (6.3.5.3)
Method
of Efficiency
Determination to be used (8.1.3,f):
33
Other:
Installed
By:
Supplier
Other:
27
Probe
Provided
By:
Supplier
Provisions
Installed Type:
Manufacturer:
Model:
34
Vibration Switch:
Rotor X
Magn X
33
Stator X
31
Provide Quote for Supervision of Installation and Erection (8.1.17)
Provide Quote
for Start-Up
Commissioning
Service
(8.1.17)
19
Driven
Equip.
Rotation
from
Non
Drive
End
of
Motor
:
Clockwise
Counterclockwise
Bi-directional
2 Viewed
Purchaser
to
provide
data
for
Supplier
to
obtain
Simulator
20
Purchaser
to
supply
Half-Coupling
or
Mass
Moment
Simulator
required
for
test
42 34
3-Phase28Fault
Current
at Machine
Terminals
(5.1.2)
Let-Through Energy (5.1.2.1):
I t (Ampere-squared
Base Frequency(ies) and Harmonics assumed present in the supply waveform(s) (8.1.3,f):
Special
Overspeed
Requirement
4.4.5.2.7):
Oscillator-Demodulator
By:(4.1.5,
Supplier MVA
Other:
Installed By:
Supplier
Other: seconds) 19
35
D.E. Bearing
Qty.:
Position(s):
Horizontal
Vertical
Axial
Other:
Overspeed Trip Point
34
Rated Load at Rated Voltage:
Stator R
Rotor R
Magn R
32
Materials to be identified with ANSI, ASTM, or ASME Numbers (8.1.18):
Motor Rotation21Viewed
fromTest
Nonwith
Drive
End
of Motor
:
Clockwise
Bi-directional
-Coupling
(6.3.1.5)
(req'd
if Supplier Counterclockwise
mounts cplg. 2.4.9.4)



V base
X/R Ratio: 20 Required
Min.Motor
startVibration
voltage
% Half
rated
43 35
Min Other:
S.C.29at Motor
Bus (4.2.3.2,
c)
MVA Supplier
at
(If Applicable)
In SensorTerm.
Housing
Other:
Location
of Terminations
(5.1.14):
Decision
In Osc.-Demodulators
Box
36
N.D.E. Bearing Qty.:
Position(s):
Horizontal
Vertical
Axial
Other:
20 Separately Powered Auxiliary Fan(s) (4.4.10.6.3): Driver Information (where
applicable)(4.1.5)
Magn X
35
Stator X
Rotor X
Type ofwhere
Load:this
Centrifugal:
Pump
Compressor
Fan
OtherAssembly (6.2.3.3)
21or specify
22 Inspection
of Equipment,
Piping
for Cleanliness
before Final
33 Information:
Contract Data (8.3)
Special Identification for Transmittals (8.3.2)
Define below
information
is to be found

 RPM

44 Other
21
Quantity
Location
Encl.
HP
RPM
Volts
Phase
Hertz
30 / Other
Bearing
Housing Seismic Sensors:
Manufacturer:
Other
37
Recommended
Vibration
Settings:
Alarm
Shutdown
Sec.
Requirements:
36 Notes
Motor
Only
36
Residual
Voltage
Open-Circuit
Time Constant:
sec. Inches
With per
Surge
Capacitors
sec.
Reciprocating
Compressor
22
Positive Displacement:
Always required
for all machines
(6.3.2) Compressor Factor "C":
23 Routine Test - Pump
34

22 Quantity
Location
Encl.
HP
RPM
Volts
Phase
Hertz
31
Sensor:
Provisions
Only
Per
API
670
(5.8.3)
Supplier
Decision
Purchaser
Defined
Installed
37
38
Alarm
ShutdownMOUNTING, WEIGHTS
Mils.
Other
24Current Pulsation
Bearing
Dimensional
& (4.2.3.6):
Alignment Checks
(6.3.2.1, k)
23 only
Per APISI618
40%Before Tests Other:
%



35 Drawings (8.5) System of Units for Drawings / Data (1.3.1):
U.S. / N.Am. Customary
SI Maximum
(Metric) only
U.S. (SI)
(U.S.)
32
Vibration Switch:
Installed
Provisions Only
Per API 670 (5.8.3)
Supplier Decision
Purchaser Defined
23 TEAAC Heat Exchanger tube material (4.4.10.8.a):
38
Horizontal
Foot Mounted
Horizontal Flange Mounted with Feet
Vertical Foot Mounted
37 Mounting:
Bearing
Dimensional
& Alignment
Checks
After



24 Format :
Provide25
Crank-Effort
Chart
or Torque-Effort
Curve No.
(8.1.3,
g):Tests (6.3.2.1, l)
36
Manufacturer To Supply Curve Data in Tabular Format (8.5.1) Define preferred Digital
39
Frequency
of Shaft Resonance
Closest
to Operating Speed:
Hertz
33
Device Provided By:
Supplier
Other:
Installed By:
Supplier
Other:
Tube materials (4.4.10.8, b): 90-10 Cu-Ni
Other Tube material:
24 TEWAC Heat Exchanger requirements (4.4.1.2.4):
38
Vertical Flange Mounted
Shaft Down
Shaft Up
Solid Shaft
Hollow Shaft
Non-Reverse Ratchet
26(4.2.2.1):
Purchaser
Supplied
Vibration Monitoring
Recording
(6.3.3.7)


25 forLoad
Characteristics
Per
NEMA
MG 1-20
Other -/ Provide
Load
Speed-Torque Curve No. (4.2.2.1, a):
37
Quantities of Documents & Drawings, and Documentation Schedule (or define source
this information)
(8.5.1):
34
Define Mounting / Hole Size if Purchaser Defines Device:
If Switch, Type:
Manual Reset
Electric
Reset
Cooling Water Conditions per 4.4.1.2.4, a
Other Cooling Water Conditions:
25
39
Flange Type:
Flange Bolt Circle Diameter:
27 Complete
Test (6.3.5.1.1)
the following:
kg-m2 at:
 RPM

26 Total Driven-Equipment/Load
Inertia Reflected
to MotorIncludes
(4.2.2.1,allc):
Wk2:
lb-ft2 or GD2:
38
After Purchaser Review of Drawings, Quantity of Certified Drawings to be provided (8.5.2):
35
D.E. Bearing
Qty.:
Position(s):
Horizontal
Vertical
Axial
Other:
26
Adapter Plate furnished with motor
40
Soleplate furnished with motor
Baseplate furnished with motor
Load
Currentinand
Slip
(6.3.5.1.1,
28 or Reducing
Efficiency
(6.3.5.1.1,
a) c):
Locked
Rotor current, PF and torque
(6.3.5.1.1,
b) intertiaFull
Ratio:
27
Speed Increasing
Gearbox
(4.2.2.1,
Note:
Affect on
to be
included
Total
Inertia
abovec)
39 36
Instruction
Manuals
Quantity
of InstructionHorizontal
Manuals to Provide
(8.7.1) (Typically
in digital format):
N.D.E.
Bearing(8.7)
Qty.:
Position(s):
Vertical
Axial suppliedOther:
27 Bearings (4.4.7.1): Hydrodynamic (4.4.7.1.1)
Sleeve (4.4.7.1.1)
Tilting Pad (4.4.7.1.1)
Antifriction (Horizontal) (4.4.7.1.3)
41 Weights: Motor Net:
lbs. Stator
lbs. Rotor
lbs. Shipping
lbs.
29
Breakdown
Torque
(6.3.5.1.1, d)
Heat
Run (6.3.5.1.1, e) V or
Speed
Curve
(6.3.5.1.1,
Noise Test at No-Load (6.3.5.1.1, g)
28 Driver
Connection
to Load:
Direct
Coupled
Gearbox
Cog Torque
Belt
Belt
Ratio: f)
40 37 Detailed
instructions
and photo's,
etc. for Supplier
disassembly
and inspection
of bearings
(8.7.4,Head
c)
In Sensor Housing
Location
of Terminations
(5.1.14):
Decision
Terminal
Box and seals
Terminal
28
Antifriction Thrust Bearing (Vertical) (4.4.7.1.5)
Hydrodynamic Thrust Bearing (Vertical) (4.4.7.1.10)
30 DC High-Potential
Test Fit
(6.3.5.1.2)



29
Motor
Shaft
Extension
(4.4.5.1.9):
Cylindrical
Taper
Fit
Integral
Flanged
41
Photos showing machine assembly steps required; including each step of bearing assembly (8.7.5)
Thrust Bearing
38 Other Monitors and Devices
29
Momentary
lbs
Momentary
lbs
Rated Rotor Temperature-Vibration
Test
(6.3.5.2.1)
(If notCapability
using
Complete
Test)
 671

30 Coupling:Specified
By: 31
Driven
Equipment
Supplier
Motor
Supplier
Per API
Downthrust
Upthrust 
Load
Copies of Applicable Certifictions, including NRTL, Material Certications (including PMI),
and other Certifications
for the machine(s)Purchaser
(8.7.6)
42
39
Monitor to Alarm for Shaft Grounding Brush Replacement (4.4.7.1.9) Describe:
30
Continuous
lbs
Continuous
lbs
(4.4.7.1.11, a)
32 Bearing Housing Natural Frequency Test (6.3.5.4.1)



31
Coupling Manufacturer:
Type:
Model:
43
Define any/all Certifications required, including materials:
40
Other Monitors or Device:
(4.4.8):
RingEnclosures)
Type Self Lubrication
(4.4.8.1) 
Machine Bearings 
Require Pressure Lube System
Yes
No
31 Lubrication
Performance
Verification
Test
(TEWAC
(6.3.5.5)

32
Supplied By: 33 Heat Exchanger
Purchaser
Driven Equipment
Supplier
Motor
Supplier
Other:
44
41 Alarm and Control Switches (5.6.1): SPDT 10 Amp 120VAC & 125VDC
Other:
Pressurized
Lube
System
(4.4.8.4)
Common
With
Driven
Equipment
(4.4.8.5)
System
Supplied
By
(4.4.8.4):
Others
32
Motor
Supplier
34 Overspeed Test (6.3.5.6; 4.1.5)



33
Motor Half-Coupling Mounted By (4.4.9.4): (requires vibration test in 6.3.1.5 when Motor Supplier mounts half-coupling)
42 Auxiliary Equipment T-Boxes (5.1.4.1): Location of Aux. Boxes (facing non-drive end):
Left Side
Right
Other:
of Oil (4.4.8.5;
4.4.8.8; 5.1.4.2):
Oil rings Included
Yes
No
35 Side
Final Rotating
Assembly33
ClearanceType/Viscosity
data storage (6.2.1.1,
e)

Driven Equipment Supplier
Motor Supplier
Other:
34
Purchaser
43
Stainless Steel Aux. Boxes/Encl. (5.1.4.1)
Cond./Cable Entry (5.1.4.1, 5.1.13):
Bottom
Left or 36 RightRadiographic
Side facing non-drive
34 end2 Define
Oil Requirements
per Bearing (8.1.4):
Flow: 2
GPM
Pressure:
QTS
Test (6.2.2.2),
Parts:


PSI Volume:
35
Coupling Inertia (4.2.2.1, c):
Wk :
lb-ft2 or GD2:
kg-m (To be included in Total Inertia above)
44 Accessory Equipment Wiring Outside Enclosure (5.1.11): Rigid Conduit
Other:
35
Heat
Loss
To
Be
Removed
per
Bearing:
kW
Ultrasonic
inspection of
analysis)

36
Mass Moment37
of Coupling
Half (4.4.6.2.1.1,f
): shaft forging (4.4.5.1.8;
or
damped unbal. response
lb-ft2 6.2.2.3)
kg-m2 (For 
36 Oil Mist Provisions (4.4.7.4) (see Guide):
Purge Oil Mist, Hydrodynamic Brg's
Pure Oil Mist, Antifriction Brg's
Oil Mist Ready, Antifriction Brg's.
38
Ultrasonic
Test
(6.2.2.3),
Define
Parts:



37
Center of Gravity of Coupling Half - drawing reference or dimensions (6.3.5.3):
Type:
37 Other:
Grease,
39
Magnetic Particle Test (6.2.2.4), Define Parts:



38 Other Information:
1
4
ITEM / TAG NO.
PURCHASE ORDER NO.
AS-BUILT
 AS-DESIGNED

JOB NO.
INDUCTION
MOTOR
ORDER NO.
API 541 5th Edition STATOR
-- DATA
SHEETS
WINDING
AND ROTORPURCHASE
REPAIR DATA
REQ. / SPEC. NO.
U.S. CUSTOMARY UNITS
1 Stator Coil Information (8.6.2.d, reference Appendix G): Coil Dimensional Drawing No.:
REVISION NO.
Page 3/4 Motor Supplier Order Data
BY
prior edition of API 541. The Purchaser and/or their representative is responsible for selections, data and revisions in Pages 1-7.
N.A.
3
N.A.
JOB NO.












Revised
Changes To Data Sheets
API 541 4th Edition
API 541 5th Edition
6 pages
12 pages
Purchaser responsible for 5 of 6 pages
Purchaser responsible for 7 of 12 pages
Purchaser data and supplier data interwoven
Separate purchaser and supplier sections
Multiple color-coded symbols, sections
One color, one symbol
Covered most 541 content
Covers all 541 content
Starting and driven equipment data on separate
pages
Single page for starting and driven equipment data
Proposal data mixed throughout 4 pages
Proposal data all on single dedicated page
Contract data by Supplier mixed throughout 5
pages
All contract data on 4 dedicated pages
Unrestricted © Siemens 2016
Page 27
Revised
Data Sheet Guide
 Vastly revised vs. 4th edition
 Covers every data element on every line in all of the Purchaser’s pages
 Gives recommendations based on working group experience
 Could be used as the basis for a tutorial on API 541 and induction machines
Unrestricted © Siemens 2016
Page 28
How to Optimize the
Use of API 541
API 541 5th Edition
Unrestricted © Siemens 2016
usa.siemens.com/oil-and-gas
How To Optimize Use of API 541







Decide what is needed for the application
Thoroughly complete the data sheet
Evaluate manufacturer responses
Maintain communications
Test to ensure satisfactory results
Install correctly
Startup, operate, monitor and maintain properly
Unrestricted © Siemens 2016
Page 30
What Is Needed for the Application
 Power, speed and voltage
 Enclosure and cooling method
 Starting requirements
 Electrical & mechanical
 Guaranteed efficiency
 Evaluation factor: $/kW
 Test method: B, F, or other
 Accessories
 Factory tests
Unrestricted © Siemens 2016
Page 31
Complete the Data Sheet
 Includes essential information
 It’s a requirement





Use data sheet guide
Equipment environment
Mechanical system characteristics
Electrical system characteristics
Auxiliary systems
Unrestricted © Siemens 2016
Page 32
Evaluate Manufacturer Responses





Review proposals in detail
Ask clarification questions
Look at alternatives
Review/discuss any comments & exceptions
Select the best option
Unrestricted © Siemens 2016
Page 33
Maintain Communications
 Face-to-face meetings
 Coordination meeting
 Verify scope of supply & expectations
 Design review meeting
 Finalize and confirm design
 Discuss & resolve issues before they affect the outcome
Unrestricted © Siemens 2016
Page 34
Test to Ensure Satisfactory Results






Testing time/cost almost always worthwhile
Test to suit application requirements
Careful with the schedule
Reduces risk of site problems
Issues easier to remedy in factory
Witness/observe where appropriate
Unrestricted © Siemens 2016
Page 35
Install Correctly





Suitable foundation requirements
Installation & alignment
Use OEM personnel when needed
Review power system and protection
Preservation prior to start-up
Unrestricted © Siemens 2016
Page 36
Startup, Operate, Monitor & Maintain
 Confirm start calculations
 Avoid excessive starts
 There is a limit!
 Availability of spares
 Commissioning & long term
 Monitor the motor condition
 Maintain per manufacturer’s instructions and user experience
Unrestricted © Siemens 2016
Page 37
Conclusions
 API 541 5th edition has significant changes
 Insulation, vibration, protection & testing
 Aimed at improving reliability & durability
 Extensive data sheet and guide enhancements
 Use the data sheets!
 Available now
Unrestricted © Siemens 2016
Page 38
Thank You For Your Time
Mark Chisholm
Principal Business Developer
Chemicals & Air Separation
Large Drives
500 Hunt Valley Road
New Kensington, PA 15068
USA
Mobile: +1 (412) 389-7469
[email protected]
siemens.com
Unrestricted © Siemens 2016
Page 39