IEC Electromagnetic Compatibility Standards for

IEC Electromagnetic Compatibility Standards for
Industrial Process Measurement and Control Equipment
Application Note
January 1998
Introduction
AN9734
TEST SEVERITY LEVEL
The purpose of the International Electrotechnical
Commission lEC 1000-4 (previously known as lEC-801)
standard is to establish a common reference for evaluating
the performance of industrial-process measurement and
control instrumentation when exposed to electric or
electromagnetic interference. The types of interference
considered are those arising from sources external to the
equipment.
The interference susceptibility tests are essentially designed
to demonstrate the capability of equipment to function
correctly when installed in its working environment. The type
of test required should be determined on the basis of the
interference to which the equipment may be exposed when
installed while taking into consideration the electrical circuit
(i.e., the way the circuit and shields are tied to earth ground),
the quality of shielding applied, and the environment in
which the system is required to work.
The lEC 1000-4 standard is divided into six sections:
lEC 1000-4-1.
Introduction
lEC 1000-4-2.
Electrostatic Discharge Requirements
lEC 1000-4-3.
Radiated Electromagnetic Field
Requirements
lEC 1000-4-4.
Electrical Fast Transient (Burst) Requirements
lEC 1000-4-5.
Surge Voltage Immunity Requirements
lEC 1000-4-6.
Immunity to Conducted Disturbances
Induced by Radio Frequency Fields
Above 9kHz
Sections lEC 1000-4-2 through lEC 1000-4-5 will be
discussed in this application note.
LEVEL
TEST VOLTAGE:
CONTACT DISCHARGE
TEST VOLTAGE:
AIR DISCHARGE
1
2kV
2kV
2
4kV
4kV
3
6kV
8kV
4
8kV
15kV
X
Special
Special
NOTES:
1. “X” is an open level.
2. The test severity levels shall be selected in accordance with the
most realistic installation and environmental conditions.
Electrostatic Discharge (ESD)
Requirements
The purpose of this test is to find the reaction of the
equipment when subjected to electrostatic discharges which
may occur from personnel to objects near vital
instrumentation.
In order to test the equipment’s susceptibility to ESD, the test
setup conditions must be established. Direct and indirect
application of discharges to the Equipment Under Test (EUT)
are possible, in the following manner:
a) Contact discharges to the conductive surfaces and to
coupling planes.
b) Air discharge at insulating surfaces.
Two different types of tests can be conducted:
1. Type (conformance) tests performed in laboratories.
2. Post installation tests performed on equipment in its
installed conditions.
CHARACTERISTICS OF THE ESD GENERATOR
LEVEL
INDICATED
VOLTAGE
FIRST PEAK CURRENT OF
DISCHARGE (±10%)
RISE TIME WITH
DISCHARGE SWITCH
CURRENT AT
30ns (±30%)
CURRENT AT
60ns (±30%)
1
2kV
7.5A
0.7 to 1ns
4A
2A
2
4kV
15A
0.7 to 1ns
8A
4A
3
6kV
22.5A
0.7 to 1ns
12A
6A
4
8kV
30A
0.7 to 1ns
16A
8A
10-76
1-800-999-9445 or 1-847-824-1188 | Copyright
© Littelfuse, Inc. 1998
Application Note 9734
TYPICAL POSITION FOR
DIRECT APPLICATION
TYPICAL POSITION FOR
INDIRECT DISCHARGE TO VCP
HORIZONTAL COUPLING PLANS
1.6m x 0.8m
TYPICAL POSITION FOR
INDIRECT DISCHARGE TO HCP
IN
SU
LA
TI
O
N
5m
0.
x P
5m C
0. V
0.1m
POWER
SUPPLY
470kΩ
RESISTOR
WOODEN TABLE 0.8m HIGH
GROUND REFERENCE PLANE
FIGURE 1. EXAMPLE OF TEST SETUP FOR TABLETOP EQUIPMENT, LABORATORY TESTS
TYPICAL POSITION FOR
DIRECT APPLICATION
INDIRECT DISCHARGE BY VCP
TYPICAL POSITION FOR
DISCHARGE TO VCP
PROTECTIVE CONDUCTOR
0.1m
5m
0.
x P
5m VC
.
0
POWER
CABLE
470kΩ
POWER SUPPLY
POWER SUPPLY
INSULATION
10cm PALLET
GROUND REFERENCE
PLANE
SIGNAL
CABLES
FIGURE 2. EXAMPLE OF TEST SETUP FOR FLOOR STANDING EQUIPMENT, LABORATORY TESTS
10-77
Application Note 9734
0.
3
m
PROTECTIVE CONDUCTOR
2m
POWER SUPPLY
GROUND REFERENCE
PLANE
FIGURE 3. EXAMPLE OF TEST SETUP FOR EQUIPMENT, POST-INSTALLATION TESTS
The only accepted method of demonstrating conformance to
the standard is the of type tests performed in laboratories.
The EUT, however, shall be arranged as closely as possible
to the actual installation conditions.
Examples of laboratory ESD test setups can be seen in
Figure 1 for tabletop equipment and in Figure 2 for floor
standing equipment.
Post installation tests are optional and not mandatory for
certification. If a manufacturer and customer agree post
installation tests are required, a typical test setup can be
found in Figure 3.
and surfaces of the EUT which are accessible to the
human operator during normal usage.
• Indirect application of the discharge: Discharges to objects
placed or installed near the EUT shall be simulated by
applying the discharges to a coupling plane (a horizontal
coupling plane under the EUT or a vertical coupling
plane).
Test Results
The results of the ESD tests are reported as follows:
1. Normal performance within the specification limits.
2. Temporary degradation or loss of function or performance
which is self-recoverable.
Test Procedure
• For conformance testing, the EUT shall be continually
operated in its most sensitive mode which shall be
determined by preliminary testing.
• The test voltage shall be increased from the minimum to
the selected test severity level.
• Number: at least 10 single discharges (in the most
sensitive polarity).
• Time interval: initial value 1 second, longer intervals may
be necessary.
• Direct application of discharge to the EUT: The static
electricity discharges shall be applied only to those points
10-78
3. Temporary degradation or loss of function or performance
which requires operator intervention or system reset.
4. Degradation or loss of function which is not recoverable,
due to damage of equipment (component) or software, or
loss of date.
lEC 1000-4-3
Radiated Electromagnetic Field Requirements
This test shows the susceptibility of instrumentation when
subjected to electromagnetic fields such as those generated
by portable radio transceivers or any other device that will
generate continuous wave (CW) radiated electromagnetic
energy.
Application Note 9734
TEST SEVERITY LEVELS
Frequency band: 27MHz to 500MHz
Small objects (25cm x 25cm x 25cm) can be tested using a
stripline antennae. This is a parallel plate transmission line to
generate an electromagnetic field as shown in Figure 6.
LEVEL
TEST FIELD STRENGTH (V/M)
1
1
Test Procedure
2
3
• The test is performed with the EUT in the most sensitive
physical orientation.
3
10
X
Special
NOTES:
• The frequency range is swept from 27 MHz to 500 MHz.
The sweep rate is in the order of 1.5 x 10-3 decades/s.
Test Results
3. “X” is an open class.
4. The test severity levels shall be selected in accordance with the
electromagnetic radiation environment to which the EUT may be
exposed when finally installed.
Test Setup
Examples of the test configuration for radiated
electromagnetic fields can be found in Figure 4 and Figure 5.
• The procedure requires the generation of electromagnetic
fields within which the test sample is placed and its operation
observed. The tests shall be carried out in a shielded
enclosure or anechoic chamber The test procedure assumes
the use of biconical and log-spiral antennae or stripline.
• All testing of the equipment shall be performed in
conditions as close as possible to the actual installation.
The results of the radiated electromagnetic field include:
• The effect of the electromagnetic field on the output of the
EUT
- As a consistent measurable effect.
- As a random effect, not repeatable, and possibly further
classified as a transient effect occurring during the
application of the electromagnetic field and as a
permanent or semipermanent field after the application
of the electromagnetic field.
• Any damage to the EUT resulting from the application of
the electromagnetic field.
The qualitative evaluation of the resultant data needs to be
assessed in terms of the existing local ambient
electromagnetic level and the specific operating frequencies.
FIGURE 4. TEST SETUP FOR RADIATED ELECTROMAGNETIC FIELD TESTS IN A SHIELDED ROOM WHERE THE ANTENNAE, FIELD
STRENGTH MONITORS AND EUT ARE INSIDE AND THE MEASURING INSTRUMENTS AND ASSOCIATED EQUIPMENT
ARE OUTSIDE THE SHIELDED ROOM
10-79
EU 4.
T
Application Note 9734
3.
T
EU
OSCILLATOR
POWER
SUPPLY
1m
POWER
AMPLIFIER
P
1m
FIELD STRENGTH
MONITOR
2.
EUT
2.
T
EU
TEST
MEASUREMENT
EQUIPMENT
FIGURE 5. TEST SETUP FOR RADIATED ELECTROMAGNETIC FIELD TESTS IN AN ANECHOIC CHAMBER, GENERAL
ARRANGEMENT OF THE EUT, FIELD STRENGTH MONITOR AND ANTENNAE
TERMINAL STRIP
FOAM PLASTIC
SECTION VIEW
METAL BOX WITH FILTERS
WOODEN PLANK
SUPPLY, INPUT AND OUTPUT
CABLES (3 + 2 + 2 WIRES)
TERMINAL STRIP (SEE FIGURE 5)
EQUIPMENT
UNDER TEST
SEE FIGURE 3
SUPPORT OF
FOAM
PLASTIC
ALL CABLES
ARE TWISTED
RF MEASURING
PROBE
SEE FIGURE 3
FRAMEWORK OF WOODEN
BEAMS (SECTION 50 x 50)
WOODEN PLANK
(SECTION 50 x 10)
TERMINAL STRIP
(9 TAGS)
BLOCKS OF WOOD
(DIMENSIONS 400 x 200 x 125)
EARTH
NOTE: Dimensions in millimeters.
FIGURE 6. TEST SETUP WITH STRIPLINE CIRCUIT
10-80
Application Note 9734
lEC 1000-4-4
Characteristics of the Fast Transient/Burst
Generator
Electrical Fast Transient (Burst) Requirements
This test is intended to demonstrate the immunity of the
equipment when subjected to interference originating from
switching transients.
TEST SEVERITY LEVELS
Open circuit output test voltage:
• Rise time of one pulse: 5ns ±30%
• Impulse duration (50% value): 50ns ±30%
• Repetition rate of the impulses and peak values of the
output voltage:
5kHz ±20% at 0.125kV
5kHz ±20% at 0.25kV
5kHz ±20% at 0.5kV
5kHz ±20% at 1.0kV
5kHz ±20% at 2.0kV
LEVEL
ON POWER SUPPLY
ON INPUT/OUTPUT
SIGNAL DATA AND
CONTROL LINES
1
0.5kV
0.25kV
• Burst duration: 15ms ±20%
2
1kV
0.5kV
• Burst period: 300ms ±20%
3
2kV
1kV
4
4kV
2kV
X
Special
Special
Test Setup
For laboratory testing, the test setup for type testing can be
shown in Figure 7 and Figure 8.
NOTES:
• Power supply lines (See Figure 7): If the line current is
higher than 100A, the “field test” shall be used.
5. “X” is an open level.
6. The test severity levels shall be selected in accordance with the
most realistic installation and environmental conditions.
• Earth connections of the cabinets: The test point on the
cabinet shall be the terminal for the protective earth
conductor (See Figure 7).
• Input/Output circuits and communication lines (See
Figure 8).
PE = PROTECTIVE EARTH
N = NEUTRAL
L1, L2, L3 = PHASE LINES
DC TERMINALS SHALL BE TREATED IN A SIMILAR WAY
CUT
EFT/B GENERATOR
<1m
I ≤ 1m (CABLE)
POWER
SUPPLY
CC
L1, L2, L3
Z1
L
N
N
PE
PE
COUPLING/
DECOUPLING
NETWORK
0.1m
INSULATING
SUPPORT
GROUNDING CONNECTION
ACCORDING TO MANUFACTURER’S
SPECIFICATION. LENGTH TO BE
SPECIFIED IN THE TEST PLAN
FILTERING
REFERENCE GROUND PLANE
CC = COUPLING CAPACITORS = 33nF
Z1 = DECOUPLING INDUCTOR > 100µH
FIGURE 7. EXAMPLE OF TEST SETUP FOR DIRECT COUPLING OF THE TEST VOLTAGE TO AC/DC POWER SUPPLY
LINES/TERMINALS FOR LABORATORY TEST PURPOSES
10-81
AC/DC
MAINS
SUPPLY
Application Note 9734
lEC 1000-4-4
the power supply terminals, AC or DC, and on the
terminals for the protective or function earth on the
cabinet of the EUT. (See Figure 9).
- Non-stationary mounted EUT, connected to the mains
supply by flexible cord and plugs: The test voltage shall
be applied between each of the power supply
conductors and the protective earth at the power supply
outlet to which the EUT is to be connected. (See Figure
10).
Electrical Fast Transient (Burst) Requirements
For field testing, the equipment or system shall be tested in the
final installed conditions without coupling/decoupling networks.
• Power supply lines and protective earth terminals
- Stationary, floor-mounted EUT: The test voltage shall be
applied between a reference ground plane and each of
- WHEN BOTH EUT ARE TESTED SIMULTANEOUSLY:
I1 = I2 ≤ 1m BETWEEN CLAMP AND EUT TO BE
TESTED
EUT
- WHEN ONE EUT ONLY IS TESTED:
I1 MIN ≥ 5m OR
I2 > 5 x I1 FOR DECOUPLING PURPOSES
EUT
AC MAINS SUPPLY
AC MAINS SUPPLY
CAPACITIVE
COUPLING CLAMP
0.1m
0.1m
0.1m
INSULATING SUPPORT
GROUNDING CONNECTION
ACCORDING TO MANUFACTURER’S
SPECIFICATION. LENGTH TO BE
SPECIFIED IN THE TEST PLAN
REFERENCE GROUND PLANE
TO EFT/B GENERATOR
INSULATING
SUPPORT
GROUNDING CONNECTION
ACCORDING TO MANUFACTURER’S
SPECIFICATION. LENGTH TO BE
SPECIFIED IN THE TEST PLAN
FIGURE 8. EXAMPLE OF TEST SETUP FOR APPLICATION OF THE TEST VOLTAGE BY THE CAPACITIVE COUPLING CLAMP FOR
LABORATORY TEST PURPOSES
PE = PROTECTIVE EARTH
N = NEUTRAL
L1, L2, L3 = PHASE LINES
PE
AC MAINS SUPPLY (BLOCKING CAPACITORS IF NECESSARY)
2,
L
3
N
TEST POINT
PE TERMINAL ON
THE CABINET
L
1,
L
EUT
33nF †
TO PERIPHERALS
EFT/B
TEST GENERATOR
AC MAINS SUPPLY
I = 1m
FLOOR
GROUNDING CONNECTION ACCORDING
TO MANUFACTURER’S SPECIFICATION. LENGTH
TO BE SPECIFIED IN THE TEST PLAN
GROUND PLANE
PROTECTIVE EARTH
FLOOR
†DC terminals shall be treated in a similar way.
FIGURE 9. EXAMPLE OF FIELD TEST ON AC/DC POWER SUPPLY LINES AND PROTECTIVE EARTH TERMINALS FOR STATIONARY,
FLOOR MOUNTED EUT
10-82
Application Note 9734
• Input/Output circuits and communication lines:
- A capacitive clamp shall be used for coupling the test
voltage into the lines. However, if the clamp cannot be
used due to mechanical problems in the cabling, it may
be replaced by a tape or a conductive foil enveloping the
lines under test. (See Figure 11).
Test Procedure
• Polarity of the test voltage: both polarities are mandatory
• Duration of the test: at least 1 minute
NORMAL PLUG PROVIDED FOR CONNECTION
OF THE EUT TO THE POWER SUPPLY
FROM EFT/B
TEST GENERATOR
TO AC MAINS SUPPLY
TO PERIPHERALS
FILTERING
EUT
Z1
CC
AC MAINS INTERCONNECTION
CC
L
Z1
CC
Z1
N
I ≤ 1m
PROTECTIVE EARTH
PE
TABLE (WOODEN)
PROTECTIVE EARTH
ACCORDING TO
SYSTEM INSTALLATION
COUPLING/DECOUPLING
DEVICE
CC = COUPLING CAPACITORS = 33nF
Z1 = DECOUPLING INDUCTOR > 100µH
FIGURE 10. EXAMPLE OF FIELD TEST ON AC MAINS SUPPLY AND PROTECTIVE EARTH TERMINALS FOR NON-STATIONARY
MOUNTED EUT
EUT
CABLETRAY
COMMUNICATION LINES
I/O CIRCUITS
THIS CONNECTION
SHALL BE AS SHORT
AS POSSIBLE
AC MAINS SUPPLY
PROTECTIVE EARTH
FLOOR
FLOOR
THE COUPLING DEVICE SHALL BE A CONDUCTIVE TAPE OR A
METALLIC FOIL IN PARALLEL OR WRAPPED AROUND AS CLOSELY
AS POSSIBLE TO THE CABLES OR LINES TO BE TESTED.
THE COUPLING CAPACITANCE OF THIS ARRANGEMENT SHALL BE
EQUIVALENT TO THAT OF THE COUPLING CLAMP.
EFT/B
GENERATOR
FIGURE 11. EXAMPLE OF FIELD TEST ON COMMUNICATIONS AND I/O CIRCUITS WITHOUT THE CAPACITIVE COUPLING CLAMP
10-83
Application Note 9734
Test Results
lEC 1000-4-5
The results are reported as:
Surge Voltage Immunity Requirements
1. Normal performance within the specification limits.
The goal of the laboratory test is to determine the
equipment’s susceptibility to damage caused by overvoltage
surges caused by circuit switching and lightning strikes.
2. Temporary degradation or loss of function or performance
which is self-recoverable.
3. Temporary degradation or loss of function or performance
which requires operator intervention or system reset.
4. Degradation or loss of function which is not recoverable,
due to damage of equipment (component) or software, or
loss of data.
TEST SEVERITY LEVELS
UNSYM LINES
LONG DATA BUS
POWER SUPPLY
CLASS
LINE TO LINE
Z=2
LINE TO GROUND
Z = 12
LINE TO LINE
Z = 42
0
SYMMETRICAL
LINES
DATA BUS
SHORT (DIST)
LINE TO GROUND LINE TO GROUND
Z = 42
Z = 42
LINE TO GROUND
No Test is Advised
1
-
0.5kV
-
0.5kV
1.0kV
-
2
0.5kV
1.0kV
0.5kV
1.0kV
1.0kV
0.5kV
3
1.0kV
2.0kV
1.0kV
2.0kV
2.0kV
-
4
2.0kV
4.0kV
2.0kV
4.0kV
-
-
5
(Note 8)
(Note 8)
2.0kV
4.0kV
4.0kV
-
X
Special
NOTES:
7. Z is the source impedance.
8. Depends on the class of the local power supply system. “X” is an open level that has to be specified in the product specification.
The class depends on the installation conditions.
Characteristics of the Test Instrumentation
• Combination wave test generator
- Open circuit output voltage . . . . . . . . . . . 0.5kV to 4.0kV
- Short circuit output current . . . . . . . . . . 0.25kA to 2.0kA
IN ACCORDANCE
WITH IEC60-2
• Test generator 10/700 µs (according to CCITT):
- Open circuit output voltage . . . . . . . . . . . 0.5kV to 4.0kV
- Short circuit output current . . . . . . . . . . . 12.5A to 100A
IN ACCORDANCE
WITH IEC469-1
FRONT
TIME
TIME TO
HALF
VALUE
RISE TIME
(10%-90%)
DURATION
(50%-50%)
Open Circuit
Voltage
1.2µs
50µs
1 µs
50µs
Short Circuit
Current
8µs
20µs
6.4µs
16µs
IN ACCORDANCE
WITH IEC60-2
IN ACCORDANCE
WITH IEC469-1
FRONT
TIME
TIME TO
HALF
VALUE
RISE TIME
(10%-90%)
DURATION
(50%-50%)
Open Circuit
Voltage
10µs
700µs
6.5µs
700µs
Short Circuit
Current
-
-
4 µs
300µs
NOTE: The surges (and test generators) related to the different
classes are:
Class 1 to 4: 1.2/50µs (8/20µs)
Class 5:
1.2/50µs (8/20ms) and 10/700µs
10-84
Application Note 9734
Test Setup
A decoupling network is used to prevent surge energy from
being propagated to the other equipment operating from the
same source during testing of the EUT. The test setup for
evaluating the EUT power supply is shown in Figures 12 15. A capacitive coupling network (preferred) or an inductive
coupling network is used for this test.
The test setup for evaluating the unshielded interconnection
lines of the EUT is illustrated in Figures 16-20. Usually,
capacitive coupling is used, but inductive coupling or
coupling via gas discharge tube (GDT) surge arrestors is
also possible.
COMBINATION WAVE
GENERATOR
COMBINATION
WAVE GENERATOR
R
R = 10Ω
C
C = 9µF
DECOUPLING NETWORK
DECOUPLING NETWORK
L
L = 20mH
C = 18µF
AC (DC) L
POWER
SUPPLY N
NETWORK
PE
L = 20mH
EUT
AC (DC)
POWER N
SUPPLY
NETWORK
EUT
PE
GROUND REFERENCE
GROUND REFERENCE
FIGURE 12. TEST SETUP FOR CAPACITIVE COUPLING ON
AC/DC LINES; LINE TO LINE COUPLING
ACCORDING TO 7.2
FIGURE 13. TEST SETUP FOR CAPACITIVE COUPLING ON
AC/DC LINES; LINE TO GROUND COUPLING
ACCORDING TO 7.2 (GENERATOR OUTPUT
FLOATING OR EARTHED)
COMBINATION WAVE
GENERATOR
DECOUPLING NETWORK
C = 18µF
L = 20mH
L1
AC (DC) POWER
SUPPLY NETWORK
L2
L3
EUT
N
PE
GROUND REFERENCE
FIGURE 14. TEST SETUP FOR CAPACITIVE COUPLING ON AC LINES (3 PHASES); LINE TO LINE COUPLING ACCORDING TO 7.2
10-85
Application Note 9734
COMBINATION WAVE
GENERATOR
R
R
R
R
C
C
C
C
R = 10Ω
C = 9µF
DECOUPLING NETWORK
L = 20mH
L1
AC (DC) POWER
SUPPLY NETWORK
L2
L3
EUT
N
PE
GROUND REFERENCE
FIGURE 15. TEST SETUP FOR CAPACITIVE COUPLING ON AC LINES (3 PHASES); LINE TO GROUND COUPLING ACCORDING TO 7.2
COMBINATION WAVE
GENERATOR
R = 40Ω
C = 0.5µF
DECOUPLING
NETWORK
AUX.
EQU.
C = 0.5µF
PROT.
EQU.
EUT
L = 20mH RL
GROUND REFERENCE
FIGURE 16. TEST SETUP FOR UNSHIELDED INTERCONNECTION LINES; LINE TO LINE COUPLING ACCORDING TO 7.3;
COUPLING VIA CAPACITORS
COMBINATION WAVE
GENERATOR
R
R
R
R
C
C
C
C
DECOUPLING
NETWORK
AUX.
EQU.
PROT.
EQU.
R = 40Ω
C = 0.5µF
EUT
L = 20mH RL
GROUND REFERENCE
FIGURE 17. TEST SETUP FOR UNSHIELDED INTERCONNECTION LINES; LINE TO GROUND COUPLING TO 7.3; COUPLING VIA
CAPACITORS
10-86
Application Note 9734
COMBINATION WAVE
GENERATOR
COMBINATION WAVE
GENERATOR
R = 40Ω
R = 40Ω
INTERCONNECTION
LINE
AUX.
EQU.
PROT.
EQU.
INTERCONNECTION
LINE
AUX.
EQU.
EUT
PROT.
EQU.
EUT
GROUND REFERENCE
GROUND REFERENCE
FIGURE 18. TEST SETUP FOR UNSHEILDED
INTERCONNECTION LINES; LINE TO LINE
COUPLING ACCORDING TO 7.3; INDUCTIVE
COUPLING FOR HIGH IMPEDANCE CIRCUITS
FIGURE 19. SIMPLIFIED TEST SETUP FOR UNSHIELDED
INTERCONNECTION LINES; LINE TO GROUND
COUPLING ACCORDING TO 7.3; INDUCTIVE
COUPLING FOR LOW IMPEDANCE CIRCUITS
COMBINATION WAVE
GENERATOR
R = 40Ω
0
1
SWITCH S
• LINE TO GROUND: POSITION 0
• LINE TO LINE: POSITIONS 1 TO 4
S
DECOUPLING
NETWORK
AUX.
EQU.
2
3
4
C = 0.1µF for frequencies of the transmission
signal below 5kHz; at higher frequencies no
capacitors are used.
C
PROT.
EQU.
EUT
L = 20mH RL
GROUND REFERENCE
FIGURE 20. TEST SETUP FOR UNSHIELDED UNSYMMETRICALLY OPERATED LINES; LINE TO GROUND COUPLING ACCORDING TO
7.3; COUPLING VIA GAS ARRESTORS
10-87
Application Note 9734
TEST GENERATOR
The internal matching resistor Rm2 (25Ω)
is replaced by external Rm2 = n x 25Ω
per conductor (for n conductors, n greater than 2).
Rm2
Example for n = 4:
Rm2 = 4 x 25 = 100Ω
Rm2 shall not exceed 250Ω
0
1
SWITCH S
• LINE TO GROUND: POSITION 0
• LINE TO LINE: POSITIONS 1 TO 4
S
2
3
4
DECOUPLING
NETWORK
AUX.
EQU.
C = 0.1µF for frequencies of the transmission
signal below 5kHz; at higher frequencies no
capacitors are used.
C
PROT.
EQU.
EUT
L = 20mH RL
GROUND REFERENCE
FIGURE 21. TEST SETUP FOR UNSHIELDED SYMMETRY OPERATED LINES (TELECOMMUNICATION LINES); LINE TO GROUND
COUPLING ACCORDING TO 7.4; COUPLING VIA GAS ARRESTORS
DECOUPLING NETWORK
L
N
POWER
SUPPLY
NETWORK
PE
EUT 2
XXXXXXX
EUT 1
XXXXXXX
COMBINATION
WAVE
GENERATOR
GROUND REFERENCE
FIGURE 22. TEST SETUP FOR TESTS APPLIED TO SHIELDED LINES AND TO APPLY POTENTIAL DIFFERENCES ACCORDING TO 7.5
AND 7.6; GALVANIC COUPLING
Test Procedure
Test Results
• Number of tests: at least 5 positive and 5 negative at the
selected points.
The results of the test are reported as follows:
• Pulse repetition: Max. 1/min.
• The maximum repetition rate depends on the built-in
protection devices of the EUT.
• The surge will be applied between lines and between lines
and ground.
• All lower levels including the selected test level must be
satisfied. For testing the secondary protection, the output
voltage of the generator must be increased up to the worst
case voltage break down of the primary protection.
10-88
1. Normal performance within the specification limits.
2. Temporary degradation or loss of function or performance
which is self-recoverable.
3. Temporary degradation or loss of function or performance
which requires operator intervention or system reset.
4. Degradation or loss of function which is not recoverable,
due to damage of equipment (component) or software, or
loss of data.