Download (PDF)

Design Specifics of High Efficiency Biomass Power Plants for fresh
wood from forestry exemplified at the 23 MWe Biomass Power
Plant Simmering / Vienna – Austria
Dipl.-Ing. Andreas Leutze, Siemens AG Power Generation, Erlangen
1. Summary
The utilization of biomass is the option within renewable energy production with the biggest rate of
growth in the coming years. Main focus will be the energy recovery from residues of agriculture and
forestry. As the resources of available biomass for producing energy are limited, maximum utilization
of the fuel is very important. The technologies applied have to be efficient, stable and cost-effective.
WIEN ENERGIE has considered this at their 23 MWe biomass power plant project in Simmering /
Vienna, Austria
2.
Introduction
WIEN ENERGIE, the Austrian Federal Forest Association (ÖBf) and District Heating Vienna will
build the plant on part of an existing old power plant site in Simmering. Some existing base plates and
parts of the old power plant can be used for the new plant. The arising power plant in Simmering will
be one of the world´s biggest biomass power plants exclusively fed with fresh wood from forestry.
The investment will be approx. 52 Mio. EURO. Siemens Power Generation is main contractor for
the turnkey supply of this plant. The steam generator will have a max. thermal output of approx. 64.6
MW. The steam generator will be a CFB (Circulating Fluidized Bed) - Boiler with reheat system. It
will be supplied by Foster Wheeler/Finland.
The plant will produce 23.4 MWe electricity in summer and 15.06 MWe plus 37 MWth for district
heating in winter. It has a fuel consumption of approx. 600.000 m³/a (approx. 23.4 t/h) forest
residual wood chips. The plant will provide electricity to approx. 45,000 households and heat to
approx. 12,000 households.
By using the optimized CFB combustion technology together with a reheat system the plant will attain
a very high efficiency. The combustion technology is also very flexible regarding the moisture of the
fresh wood.
Boiler erection will start at the end of April 2005.
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 1.
3. Plant Overview
The main focus of the plant is electricity generation throughout the year (base load power plant,
design point operating hours > 8.000 h/a) and in winter supply of district heat with the highest
possible number of operating hours at full load and with high availability.
The power plant will be erected on the existing Simmering power plant site and some existing
buildings can be used. Some of the existing buildings, for example the old boiler house and turbine
house, were demolished by the customer (picture 1). The base plates of the old boiler and of the old
steam turboset can be reused for the new components (picture 2). The old components like feed
water tank, the boiler feed water pumps, main condenser, condensate pumps and cooling water
pumps and part of the piping system are replaced by new ones.
Picture 1: Demolition of the old boiler and turbine house
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 2.
Picture 2: Existing turbine base plate will be reused
The general overview of the power plant concept is shown in picture 3.
Picture 3: Flow scheme of the biomass power plant Simmering
Andreas, you should have a key for this diagram in English if the picture text is in German
The main systems of the power plant are the fuel input (bunker), the fuel storage (silo) and the fuel
transport systems, the steam generator (CFB boiler), the flue gas cleaning (dry sorption) and the
power island (extraction condensing turbine).
In the following chapters the main data of the systems are presented.
3.1 Fuel Handling
3.1.1 Fuel Specification
The biomass which will be burned in Simmering is mainly fresh wood chips. The kind and percentage
of different fuels that will be burned is shown in table 1.
Pos
Fuel
1.
1.1.
2.
2.1.
3.
4. Fresh wood
Wood chips from forestry
5. Bark
Bark
6. Untreated waste wood
Key. No.
acc.
ÖNORM S
2100
Portion
75 Ma. % - 100 Ma. %
17101
0 Ma. % - 10 Ma. %
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 3.
3.1.
3.2.
3.3.
3.4.
4.
4.1.
Chips from untreated wood
Waste wood
Wood wool, uncontaminated
Garden and park waste
7. Natural Gas
Natural gas H
17102
17201
17203
91701
Together
0 Ma. % - 15 Ma. %
Auxiliary firing, for startup of the plant
Table 1: Fuel specification
Mainly fresh wood (water content approx. 40%) is burned during the year. The fuel mass flow in the
design point is approx. 184.000 t/a. But the plant also needs to be designed for each fuel mixture
that is specified in table 1. In the fuel mixture a maximum waste wood fraction of 30.000 t/a (water
content approx. 15%) will be burned. The proportions of relevant chemical elements in the fuel are
shown in table 2.
Element
Portion
Sulfur (S)
0,15 wt-% dr
Chlorine (Cl)
0,10 wt-% dr
Nitrogen (N)
1,00 wt.-% dr
Sodium (Na)
400 mg/kg dr.
Kalium (K)
3.500 mg/kg dr.
Bulk density
150 – 500 kg/m³
Table 2: Parts of the elementary analysis of the fuel
3.1.2 Fuel Transport/ Storage
The fuel is transported by trucks to the power plant and unloaded into a bunker. The wood chips are
transported via moving floors and conveyors into a storage silo (capacity 7.500 m³).
Before the wood chips are stored in the silo there is a magnetic separator that removes iron parts
and an oversize treatment that eliminates oversized material. So it is assured that the stored fuel
meets the demands of the firing system.
From the storage silo the appropriate biomass is transported into the daily silo of the steam generator
(capacity 50 m³).
3.2 Steam Generator
The steam generator will be supplied by Foster Wheeler and is a CFB (Circulating Fluidized Bed) –
Boiler with a reheat. The steam generator is designed for a thermal load of 64.6 MWth and the live
steam operating data are 120 bar/ 520°C and 16 bar/ 520°C in the hot reheat. The final superheater
is an INTREX superheater, a special design feature from Foster Wheeler. For bed material natural
sand is used. For reduction of NOx a SNCR (Selective Non-Catalytic Reduction) in combination
with a SCR (Selective Catalytic Reduction) is applied. The reheat system can increase the efficiency
of the plant considerably.
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 4.
During winter operation with heat extraction the plant will reach a total efficiency of approx. 83%.
During summer no heat extraction is in operation and the plant will produce a power output of
approx. 23.4 MWe gross with an electrical efficiency of 36%.
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 5.
Thermal boiler output
Fuel
Max. 64.6 MWth
Fresh wood chips, bark, untreated waste
wood, natural gas (start-up burner)
Turbine output in summer
23.4 MWel on the generator terminal
Turbine extraction
31 – 48 t/h at 3 bar
Live steam parameters
23.4 t/h, 120 bara, 520°C (inflow turbine)
Total efficiency
Max. 83 %, (brutto electrical approx. 36,4 %)
Table 3: Overall technical data of the Simmering plant
3.3 Flue Gas Treatment
The nominal flue gas flow is approx. 100.000 Nm³/h. By dosing calcium hydroxide (Ca(OH)2) and
filtering through a bag house filter, the emissions of dust, acid gases like SO2 and HCl are reduced
below the imposed limits. The limits for clean gas emissions are shown in table 4.
Emissions (half hour average
values at 13% O2)
Dust
CO
NOx
Corg
SO2
HCl
HF
Dioxine, Furane
NH3 at 0% O2
mg / Nm³
10
100
50
20
50
10
1
0.1 ng/Nm³
10 mg/Nm³
Heavy metals emissions are reduced by the dosing of activated coal.
3.4 Balance of Plant
The Balance of Plant (BoP) consists mainly of the live steam system, cold and hot reheat system,
condenser, main condensate system with LP-Preheater and feedwater system with HP-Preheaters,
steam air-preheater system, district heating system (single stage) and condensate drainage systems
(see also picture 3).
3.5 Steam Turboset
During summer the turboset is operated in 100% condensing mode and produces a nominal electrical
power of 23.4 MWe (generator output). The necessary auxiliary power of the plant is 2.17 MWe.
The maximum produced electrical power of the plant is approx. 24.5 MWe.
During winter the turboset is operated in extraction/condensing mode and produces a nominal
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 6.
electrical power of 15.06 MWe and a thermal power of 37 MWth for district heating. During the
winter season the plant runs at its highest efficiency (approx. 83%).
4. Conclusion
As fresh wood is a rather valuable and expensive fuel the Simmering biomass power plant was
designed for very high efficiency. The CFB boiler technology with reheat system, LP-and HPPreheating systems guarantees a maximum fuel utilization for saving resources of fresh wood. The
operation of the plant reduces Vienna´s CO2 emissions by 144.000 t/a CO2 and saves approx.
60.000 t/a coal.
Design Specifics of High Efficient Biomass Power Plants exemplified at Plant Simmering / Vienna – Austria
A. Leuze © Siemens AG 2005. All rights reserved.
feb. 2005 - pag. 7.