DCIT #31 PLENARY
DCL Trials Update
3/13/2014
Matt Maki
DCL Trials Lead
Federal Aviation
Administration
DTAP Build 7.1 Schedule Update
•
Build 7.1 Limited Climb Via SID Compliance:
-
•
Interim Build with KEWR focus
UM169 CVS UL when MAINT ALT Set to NONE
National 7110.65 CVS ATC Implementation set for April 3
Trials will seek EWR/MEM CVS DTAP waiver thru May 15
EWR ATC FAT Input Planned
Build 7.1 Estimated Schedule:
-
April 14-15:
April 16:
April 17-25:
April 28 - May1:
FAT at Thales
Install at FAATC
Testing at FAATC
Install and SAT at MEM and EWR (Parallel
installs)
Federal Aviation
Administration
DTAP Build 7.2 Schedule Update
•
Build 7.2 Full Climb Via SID Compliance:
-
•
Compliance with full 7110.65 CVS Changes
CVS, CVS Except Maintain, Maintain ALT Selections
Longer WJHTC lab testing period expected due to CVS scale
Build 7.2 Estimated Schedule:
-
June 11-12:
June 13:
June 16 - July 3:
July 7-10:
B7.2 FAT at Thales
Install at FAATC
Testing at FAATC
Install and SAT at MEM and EWR (Parallel
installs)
Federal Aviation
Administration
KEWR DCL Trials Status Update
•
UAL, FDX MD11/B777 Daily Ops Ongoing:
-
•
Open OPR reports diminishing
UAL FRC DCL Filing Error Reductions
Resuming of UAL B767 ops expected next month+
UPS Starts Daily MD11/B767 Ops March 15:
-
•
Approx. 24 Ops/week expected
AFS-50/400/2P Approval letter to UK CAA pending:
-
BAW, SAS, DLH CAA Approval letters back to FAA pending
BAW approval expected first
Federal Aviation
Administration
KEWR DCL Trials Status Update
•
NetJets Trials Participation at KEWR:
-
•
NetJets confirmed interest in participating
Kick off Telcon set for March 19 with AOC and Pilot Reps
Bombardier Global Express 5000/6000 aircraft FANS equipped
Bombardier Challenger 350 FANS/VDL2 upgrades expected in
July
1-2 DCL flights/week from KEWR expected
March 1-4 ZNY 72 HR ERAM Testing Complete:
-
Test was successful
Next 72 HR ERAM run expected April 5-8
Federal Aviation
Administration
Federal Aviation
Administration
KMEM DCL Trials Update
•
DTAP Running Stable:
-
•
Unplanned Recons minimized – 1 event since last DCIT
Server 1, 2 Re-starts On-going (Tues/Fri)
DTAP Processing 20-40 FDX DCL ops per push
Route Revisions remain minimal/none in #s
MEM ATC confirms use of CVS phraseology:
-
Planned CVS waiver will include MEM
Federal Aviation
Administration
DCL Ops Advantages During
Upcoming SWAP Season
Federal Aviation
Administration
Questions ?