MEM/EWR ATCT DCL Trials
Status / Overview
DCIT #26 Plenary
From:
Matt Maki / DCL Trials Lead
Date:
08.22.2013
Federal Aviation
Administration
DTAP SW Patch 5.1 Update
•
Included Requirements:
SID NONE
MAINT ALT NONE
Double TO
Dual Contact/Drop Down Remarks
•
Thales development work on-going
•
Expected delivery to FAA for initial WJHTC testing late
Sept, early Oct
•
Functional Testing, SAT at MEM, EWR planning
Federal Aviation
Administration
2
Build 7 Update
•
Down selected Requirements Proposal
Evaluation Underway
•
Budget, Scope, Cost Considerations
•
Arrival Procedure Processing Consideration
Federal Aviation
Administration
3
MEM/EWR Trials Schedule
•
MEM FDX Full Fleet 24x7 Trials Starts Sept. 3, 2013:
B777 (15) and MD-11 (20) completed minimum successful
ops during Limited Trials
B777 full functionality, MD-11 CAF only until DTAP Patch 5
SW implemented in Oct
FDX CMO Paperwork Complete, ATC Training Starts 8/26
•
EWR Limited Trials to continue thru SWAP:
-
BAW, UPS, FDX, UAL, DLH participating
SAS currently standing down over Airbus CLR7+ FMS Issue
Federal Aviation
Administration
4
Initial UAL EWR DCL Ops
•
UAL Starting Limited Trials B767 Ops at EWR Sept. 3 (3-5 flights):
Initial CMO paperwork complete
EWR CMO Update to Planned initial 3-5 daily flights (8/21Trent)
UAL956 - 1755 GVA * (Pending FANS retrofit)
UAL964 - 1820 AMS * (Pending FANS retrofit)
UAL992 - 1845 ZRH
UAL904 - 1915 IST
UAL847 - 2155 EZE
•
Trials Ops Support on site at EWR Sept 3-5
•
UAL planning ~20 B777 EWR domestic/international operations on
rolling basis starting post SWAP
Federal Aviation
Administration
5
DCL Ops Reporting
•
Currently manual ops reports from MEM/EWR,
HADDS
•
Long Term automated ops reporting
implementation (Harris/Boeing planning)
•
Needed for ops tracking during 24x7 full Trials
Federal Aviation
Administration
6
8/22z EWR DTAP Alert
Federal Aviation
Administration
7
8/22z FDX1202
Federal Aviation
Administration
8
MEM DCL Ops Since 4/17/13 –
Start of Limited Ops Trials
CAF
Initial
UM79
Initial
UM80
UM79
Rev
UM80
Rev
Total
UM
WILCO
Aircraft
Airline
Total DCL
Flights
MD11
FDX
35
34
0
1
9
5
49
B777
FDX
16
14
1
1
6
2
24
Current Up Thru 8/21/13
Federal Aviation
Administration
9
MEM DCL Ops Since 4/17/13 Lessons Learned
Unplanned
Voice
Clearance/
PDC
Issued
FRC DCL Filing
Issues
(Not Filed or Within
First 22
Characters) and/or
Crew Status (Not
DCL Approved)
DTAP
Automation –
FANS Avionics
Issues/Testing
HADDS/
CSP/
Network
Issues
ATC/FD
Coordination
AC
Mechanical/
Diversions
27
14
6
2
4
1
Current Up Thru 8/21/13
Federal Aviation
Administration
10
EWR DCL Ops Since 5/16/13 - Start of Limited Ops Trials
CAF
Initial
UM79
Initial
UM80
UM79
Rev
UM80
Rev
Total
UM
WILCO
14
12
0
2
5
4
23
FDX
3
2
1
0
0
0
3
BAW
15
15
0
0
0
0
15
FDX
3
3
0
0
0
0
3
UPS
2
1
1
0
0
0
2
UAL
0
0
0
0
0
0
0
A333
SAS
2
1
1
0
0
0
2
A343/6
DLH*
52
52
0
0
1
0
53
Aircraft
MD11
B777
B767
Airline
Total DCL
Flights
UPS
Current Up Thru 8/21/13
* HADDS Check
Federal Aviation
Administration
11
EWR DCL Ops Since 5/16/13 Lessons Learned
Unplanned
Voice
Clearance/
PDC
Issued
FRC DCL Filing
Issues
(Not Filed or Within
First 22
Characters) and/or
Crew Status (Not
DCL Approved)
DTAP
Automation –
FANS Avionics
Issues/Testing
HADDS/
CSP/
Network
Issues
ATC/FD
Coordination
AC
Mechanical/
Diversions
51
35
9
3
2
2
Current Up Thru 8/21/13
Federal Aviation
Administration
12
MEM FDIO Test NCP Update
•
Case File approved thru CMRT
•
Aug CCB board approval expected
Federal Aviation
Administration
13
Questions ?