DCIT_20_Plenary_Presentation_FAA.ppt

Data Communications
Program
DCL Trials DCIT Update
MEM ATCT
To:
DCIT Plenary
From:
Matt Maki
Date:
12.06.2012
Federal Aviation
Administration
Agenda
•
DTAP Development Status:
-
•
DTAP Development/Milestone Deliveries
Trials Schedule Update
On-Going / Completed Trials Activities Status:
-
DTAP Certification
MEM Training & Procedures
Trials Metrics Development
•
Trials CSP Service Update
•
EWR Trials – Schedule/Planning Discussion
Federal Aviation
Administration
DTAP Milestone Deliveries
•
SE2020 Deliverables / DTAP Development:
-
Limited Trials Build undergoing Functional Testing @ WJHTC
-
-
Fixes previous HIGH/MED-HIGH level PTRs
Installed @ MEM ATCT 12/3 for continued Functional /FDX-UPS Testing
CAF, UM80, UM79 (Non INT), AOC DM (non SI Doc compliant)
Full Trials Build scheduled estimated for delivery to the
WJHTC on Jan 22
-
Initial UM79 requirement included (ERAM FIR Boundary limits)
UM83 and discovered ‘out of scope’ minimum Trials requirements included
Additional requirements from testing included
Represents ‘full fleet’ Trials functionality
Federal Aviation
Administration
MEM Limited Ops Trials (~ 3 Ops/Day - 2
Weeks)

Nov 27:
Limited Ops Build installed on WJHTC Data Comm lab DTAP
Limited Ops Build installed on designated Training DTAP3
•
Dec 3-14 (WJHTC & MEM Functional/Pre-SAT Testing)
Limited Ops Build installed on MEM ATCT DTAP
Limited Ops Build Functional Testing @ MEM ATCT (Bench and FDX/UPS aircraft avionics planned)
Limited Ops Build WJHTC Functional Test summary review
•
Dec 17-20 Boeing / Airbus Bench Testing Window
•
Dec 24-Jan 1 (Holiday Break)
•
Jan 2-7:
OT2 @ MEM (Jan 2)
Limited MEM ATC Training (DTAP3 Training machine)
Formal MEM SAT (Jan 3-4)
Trials Start Checkpoint – Go/No Go (Jan 7)
•
Jan 7-21: Buffer
•
Jan 22 – TRIALS START (Jan 14 Target Start Option)
Federal Aviation
Administration
MEM Limited Ops Trials Timeline
Functional
Testing @
WJHTC & MEM
11/27 – 12/14
NOV
Additional
Functional
Testing
BUFFER
Holiday
Break
12/24 – 1/2
12/14 – 12/24
DEC
OT2,
ATC
Training,
SAT @
MEM
BUFFER
1/7 – 1/21
Limited Ops
Trials Window
(TBD Ops/Day –
2 Weeks)
1/22 – 2/10
1/2 – 1/7
FEB
JAN
Federal Aviation
Administration
MEM Full Functionality Trials Ops
•
Dec 10-17:
Final DTAP SE2020 Contract Build 6 Requirements/Delivery Date Implementation
•
Jan 22-Feb 6:
Full Functionality Build installed on WJHTC DTAP – Functional Testing Window
FDX Pilot Training 30 Day Notice Given (FF Build Accepted for Trial Ops – 2/4)
•
Jan 29-Feb 8:
Conduct OT3 @ MEM (1/29)
Conduct Formal ATC DTAP Training @ MEM
•
-
Feb 10-Feb 15:
END OF LIMITED OPS TRIALS (2/10)
Install Full Functionality Build on MEM DTAP (2/11)
Pre-SAT, Functional Testing Activities
FDX GOC Training 2 Week Notice Given
•
Feb 18-22:
Formal Full Functionality Build SAT @ MEM
Full Trials Go/No-Go Checkpoint (2/22)
•
March 4: FULL FUNCTIONALITY TRIALS START ~50 flights (2/25 Target Start Option)
Trials Procedures Shake Out
Federal Aviation
Administration
MEM Full Functionality 24x7 Ops
Trials
•
April 4 MEM Full Fleet Trials
•
Starts 120 Day Trials Review
Checkpoint Timer
Federal Aviation
Administration
MEM Full Ops Trials Timeline
FDX Pilot
Training 30 Day
Notice – 2/4
Functional
Testing @
WJHTC
1/22 – 2/6
FDX GOC
Training 14 Day
Notice – 2/15
End of
Limited
Ops Trials,
MEM DTAP
Upgrade
2/10 – 2/15
SAT @
MEM, Trials
FF GO
Checkpoint
2/18 – 2/22
Buffer
Full Functionality Trials Start,
Procedures Shake Out (~50 DCL
Flights)
Full
Functionality
24x7 Trials Ops
3/4 – 4/4
4/4 + 120 Days
OT3 &
ATC
Training
@ MEM
1/29 – 2/8
JAN
FEB
APR
MAR
Federal Aviation
Administration
Tech Ops DTAP Certification
•
Certification on Track to enable Trials start:
-
•
Tech Ops reps completed draft DTAP Certification
procedures at the WJHTC lab on 10/10 & 11
Procedures / FAM Training complete
AJW-13 to propagate Notice to field / trials sites
FSEP office notified FTI that Cert / FAM
procedures are satisfactory:
-
•
Allows FSEP DTAP log entry & FTI check-off
Train MEM Tech Ops Scheduled for December 17:
-
Trained MEM Tech Ops reps credentialed via District Mgr.
Federal Aviation
Administration
MEM Training and Procedures
•
MEM Training and SAT Procedures complete:
-
•
Limited MEM DTAP Training scheduled for Jan 2-7 2013
Full MEM DTAP Training planned for Jan 29 – Feb 8
MEM Trials SAT draft released for internal review 12/3
FDX Training:
-
FDX AOC/Dispatch training (2 weeks advance notice req)
FDX Pilot training (30 day advance notice req)
FAA CMO LOA (2 weeks advance notice req)
Federal Aviation
Administration
Trials Metrics Development
•
DTAP log file analysis underway:
-
•
Thales to provide tools for decoding/presenting DTAP log file
data
Summary Trials data analysis planned
DCIT Plenary Update
Independent Safety Assessment Office (AJI-321)
planning Trials evaluation and analysis:
-
Trials team to provide ISA with Trials procedures, metrics and
test plans
Federal Aviation
Administration
Trials CSP Service Update
•
ARINC/SITA Current Agreements:
-
ARINC Trials service being extended from current 12/31
POP end
Additional ARINC extensions available if required
SITA service contract extended on month x month basis
Federal Aviation
Administration
EWR Trials Schedule/Planning
•
Verify limited Trials start @ EWR can commence before the
MEM 120 day review checkpoint
•
EWR Trials Start in April is a challenge for DCP:
-
•
EWR ATC accepts final MEM DTAP functionality for initial Trials
implementation (Dec, DCIT Ops Mgt)
EWR CHI functionality updated utilizing a TBD DTAP release
EWR May-Sept Implementation Freeze Out
EWR Trials Implementation Activities Underway:
-
Meeting at facility with ATC and Tech Ops Mgt (12/17)
FTI Telco/Network Connectivity Order Initiated
DTAP ZNY HADDS/OARS interface configuration Initiated
HADDS, FDIO Test NCP development Initiated
Equipment Implementation goal in March
Initial operators include UAL, FDX, UPS, LFT
Federal Aviation
Administration
Questions ?